Maintenance Technology September 2016 - 39

SAP TIPS AND TRICKS Improve Your Planning Efficiency Kristina Gordon, DuPont ACCOMPLISHING DAILY WORK in a reliability and maintenance operation involves performing several critical functions, among them planning, scheduling, identification of equipment criticalities, and work history. In many cases, it seems to take forever to complete even the smallest task in SAP. That does not need to be the case. What follows are SAP solutions for four of the most common maintenance-planning questions. Q A What is the most efficient way to extract a list of proposed job plans (work orders)? In transaction IW38, create a variant. A variant saves the selection of values that you use to run a report or transaction the same way every time. You can create as many variants in one transaction as you need, depending on the data that you are interested in seeing. Variants can be global, meaning everyone in your organization can see and choose to run, or you can make the variant user specific. This hides your variant and only allows you as the creator to use it. Selection criteria may include your maintenance plant/ planning plant, orders outstanding and in progress, and orders that have no date limitations. You may also want to exclude work orders that have been released or TECO'd. Use other filters as appropriate, such as plant section and work center. Once you complete the selection process, click the save button and the variant screen will pop up allowing you to save the selection you have entered. When creating a user-specific variant you will always name the variant U_(user name given to you to log into SAP). Now that you have a This example standard selection criteria, you illustrates the will be pulling your work orders process of extracting up the same way every time. a list of proposed job plans. Q How can I tell if my material will be available and ready on the day I plan my job? A In transaction IW32, after adding your components to the work order, click the (material availability, overall) icon in the tool bar at the top of the page. The material-availability icon compares the basic start date of the work order with the material delivery time to verify whether the part will be on site when needed. SAP will display a message to indicate that all requested materials are available. Otherwise, it will display the material numbers that have conflicting delivery dates. Q If I am planning a job months in advance but want my materials received as soon as possible for kitting or job readiness, how can I request my material delivery time be changed? A Under the components tab of your work order, highlight the material for which you would like to have the delivery date moved. The Gen. Data tab displays your componentThen click on the Gen. detail screen. data tab at the bottom. This brings up your component-detail In the offset field, enter the number of days screen. The requirements materials are needed in advance, using a date will be displayed negative sign. and it should match the work-order start date. In the offset field, enter the number of days the materials are needed in advance with a negative sign, then enter the unit of measure for days. Click the enter button and you will be asked if this date can be met. Click the enter button again and the requirements date for the materials will move to the new requested date. This feature is for stock and non-stock items. It works with MRP to create your purchasing documents and updates the reservations list for onsite materials. Q If I have created a task list and need to move it to my work order, how can I do this without copying and pasting every line? A In the tool bar at the top of the page in IW32, click on Extra>Task List Selection>Direct Entry. In the pop-up box you will be asked to click the radio button next to functional location task list, equipment task list, or general task list. Enter the group and group counter of the task list you would like to import. Click the check mark Kristina Gordon is SAP Program Consultant at the DuPont, Sabine River Works plant in West Orange, TX. If you have SAP questions, send them to editors@maintenancetechnology.com and we'll forward them to Kristina. SEPTEMBER 2016 MAINTENANCETECHNOLOGY.COM | 39 http://www.MAINTENANCETECHNOLOGY.COM

Table of Contents for the Digital Edition of Maintenance Technology September 2016

Editorial
Uptime
On The Floor
Old-School Approach To New-World Technology
Art Meets Reliability Science
Commit To Safety
Robot-Human Interaction Getting Safer
Sanitary, Stainless Conveyors Not The Same
Reduce Hidden Process-Safety Costs
Pace Your Reliability Program
Win The War With 'Lubrication By Design'
SAP Tips And Tricks
Understand Pump Vibration
Select The Right Relay
Bearing Care
Clear Up HOA Confusion
Potato Waste Becomes Clean Water, Energy
Products
Showcase
Ad Index
Final Thought
Maintenance Technology September 2016 - 1
Maintenance Technology September 2016 - Cover1
Maintenance Technology September 2016 - Cover2
Maintenance Technology September 2016 - 1
Maintenance Technology September 2016 - 2
Maintenance Technology September 2016 - 3
Maintenance Technology September 2016 - Editorial
Maintenance Technology September 2016 - 5
Maintenance Technology September 2016 - Uptime
Maintenance Technology September 2016 - 7
Maintenance Technology September 2016 - On The Floor
Maintenance Technology September 2016 - 9
Maintenance Technology September 2016 - Old-School Approach To New-World Technology
Maintenance Technology September 2016 - 11
Maintenance Technology September 2016 - 12
Maintenance Technology September 2016 - 13
Maintenance Technology September 2016 - 14
Maintenance Technology September 2016 - 15
Maintenance Technology September 2016 - Art Meets Reliability Science
Maintenance Technology September 2016 - 17
Maintenance Technology September 2016 - 18
Maintenance Technology September 2016 - 19
Maintenance Technology September 2016 - Commit To Safety
Maintenance Technology September 2016 - 21
Maintenance Technology September 2016 - 22
Maintenance Technology September 2016 - 23
Maintenance Technology September 2016 - Robot-Human Interaction Getting Safer
Maintenance Technology September 2016 - 25
Maintenance Technology September 2016 - Sanitary, Stainless Conveyors Not The Same
Maintenance Technology September 2016 - 27
Maintenance Technology September 2016 - 28
Maintenance Technology September 2016 - Reduce Hidden Process-Safety Costs
Maintenance Technology September 2016 - 30
Maintenance Technology September 2016 - Pace Your Reliability Program
Maintenance Technology September 2016 - 32
Maintenance Technology September 2016 - 33
Maintenance Technology September 2016 - 34
Maintenance Technology September 2016 - 35
Maintenance Technology September 2016 - Win The War With 'Lubrication By Design'
Maintenance Technology September 2016 - 37
Maintenance Technology September 2016 - 38
Maintenance Technology September 2016 - SAP Tips And Tricks
Maintenance Technology September 2016 - Understand Pump Vibration
Maintenance Technology September 2016 - Select The Right Relay
Maintenance Technology September 2016 - Bearing Care
Maintenance Technology September 2016 - 43
Maintenance Technology September 2016 - Clear Up HOA Confusion
Maintenance Technology September 2016 - Potato Waste Becomes Clean Water, Energy
Maintenance Technology September 2016 - 46
Maintenance Technology September 2016 - 47
Maintenance Technology September 2016 - 48
Maintenance Technology September 2016 - 49
Maintenance Technology September 2016 - 50
Maintenance Technology September 2016 - 51
Maintenance Technology September 2016 - 52
Maintenance Technology September 2016 - Showcase
Maintenance Technology September 2016 - Ad Index
Maintenance Technology September 2016 - 55
Maintenance Technology September 2016 - Final Thought
Maintenance Technology September 2016 - Cover3
Maintenance Technology September 2016 - Cover4
Maintenance Technology September 2016 - 62
Maintenance Technology September 2016 - 63
Maintenance Technology September 2016 - 64
Maintenance Technology September 2016 - 65
Maintenance Technology September 2016 - 66
Maintenance Technology September 2016 - 67
Maintenance Technology September 2016 - 68
Maintenance Technology September 2016 - 69
Maintenance Technology September 2016 - 70
Maintenance Technology September 2016 - 71
Maintenance Technology September 2016 - 72
Maintenance Technology September 2016 - 73
Maintenance Technology September 2016 - 74
Maintenance Technology September 2016 - 75
Maintenance Technology September 2016 - 76
Maintenance Technology September 2016 - 77
Maintenance Technology September 2016 - 78
Maintenance Technology September 2016 - 79
Maintenance Technology September 2016 - 80
Maintenance Technology September 2016 - 81
Maintenance Technology September 2016 - 82
Maintenance Technology September 2016 - 83
Maintenance Technology September 2016 - 84
Maintenance Technology September 2016 - 85
Maintenance Technology September 2016 - 86
Maintenance Technology September 2016 - 87
Maintenance Technology September 2016 - 88
Maintenance Technology September 2016 - 89
Maintenance Technology September 2016 - 90
Maintenance Technology September 2016 - 91
Maintenance Technology September 2016 - 92
Maintenance Technology September 2016 - 93
https://www.nxtbook.com/atp/MaintenanceTechnology/efficient-plant-jan-feb-2024
https://www.nxtbook.com/atp/MaintenanceTechnology/efficient-plant-april-2022
https://www.nxtbook.com/atp/MaintenanceTechnology/efficient-plant-october-2021
https://www.nxtbook.com/atp/MaintenanceTechnology/efficient-plant-june-2021
https://www.nxtbook.com/atp/MaintenanceTechnology/epapril2021
https://www.nxtbook.com/atp/MaintenanceTechnology/epmarch2021
https://www.nxtbook.com/atp/MaintenanceTechnology/epjanfeb2021
https://www.nxtbook.com/atp/MaintenanceTechnology/epjulyaug2020
https://www.nxtbook.com/atp/MaintenanceTechnology/epjune2020
https://www.nxtbook.com/atp/MaintenanceTechnology/epmay2020
https://www.nxtbook.com/atp/MaintenanceTechnology/epapril2020
https://www.nxtbook.com/atp/MaintenanceTechnology/epmarch2020
https://www.nxtbook.com/atp/MaintenanceTechnology/epfeb2020
https://www.nxtbook.com/atp/MaintenanceTechnology/epjan2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epnovdec2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epseptoct2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epmay2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epapril2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epmarch2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epfebruary2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epjanuary2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epdecember2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epnovember2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epoctober2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epseptember2019
https://www.nxtbook.com/atp/MaintenanceTechnology/epaugust2018
https://www.nxtbook.com/atp/MaintenanceTechnology/0818schneider
https://www.nxtbook.com/atp/MaintenanceTechnology/epjuly2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epjune2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epmay2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epapril2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epmarch2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epfebruary2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epjanuary2018
https://www.nxtbook.com/atp/MaintenanceTechnology/epdecember2017
https://www.nxtbook.com/atp/MaintenanceTechnology/epnovember2017
https://www.nxtbook.com/atp/MaintenanceTechnology/epoctober2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtsept2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtaugust2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtjuly2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtjune2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtmay2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtapril2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtmarch2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtfebruary2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtjanuary2017
https://www.nxtbook.com/atp/MaintenanceTechnology/mtdecember2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtnovember2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtoctober2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtseptember2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtaugust2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtjuly2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtjune2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtmay2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtapril2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtmarch2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtfebruary2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtjanuary2016
https://www.nxtbook.com/atp/MaintenanceTechnology/mtdecember2015
https://www.nxtbook.com/atp/MaintenanceTechnology/mtnovember2015
https://www.nxtbook.com/atp/MaintenanceTechnology/mtoctober2015
https://www.nxtbook.com/atp/MaintenanceTechnology/mtseptember2015
https://www.nxtbook.com/atp/MaintenanceTechnology/MTAugust2015
https://www.nxtbook.com/atp/MaintenanceTechnology/MTJuly2015
https://www.nxtbook.com/atp/MaintenanceTechnology/MTJune2015
https://www.nxtbook.com/atp/MaintenanceTechnology/M
https://www.nxtbook.com/atp/MaintenanceTechnology/0415endress
https://www.nxtbook.com/atp/MaintenanceTechnology/MTApril2015
https://www.nxtbook.com/atp/MaintenanceTechnology/MTMarch2015
https://www.nxtbook.com/atp/MaintenanceTechnology/MTFebruary2015
https://www.nxtbook.com/atp/MaintenanceTechnology/MTJanuary2015
https://www.nxtbook.com/atp/MaintenanceTechnology/MTDecember2014
https://www.nxtbook.com/atp/MaintenanceTechnology/MTNovember2014
https://www.nxtbook.com/atp/MaintenanceTechnology/MTOctober2014
https://www.nxtbook.com/atp/MaintenanceTechnology/MTSeptember2014
https://www.nxtbook.com/atp/MaintenanceTechnology/MTAugust2014
https://www.nxtbook.com/atp/MaintenanceTechnology/MTJuly2014
https://www.nxtbookmedia.com