ASHRAE Journal - September 2013 - 47

Technical FeaTure
Fea

commissioning authority should also ensure proper
training of the building owner or operator to ensure
persistent savings. User interfaces, calibration steps
and equipment locations must all be taught and well documented to the operator during this training step, allowing them to make ongoing adjustments for occupant
complaints and building modifications.
Calibration and functional testing controls are steps in
this commissioning process that are critical to successful implementation and energy savings.6 Calibration
is sometimes blended into the functional testing task,
though ideally the calibration would be finished and
then separate functional tests completed to ensure steps
from installation to calibration were done correctly.7 In
an ideal process, the contractor would complete start-up
and calibration, and a commissioning authority would
simply verify that the calibration and necessary illumination tests had occurred. In practice, it is most important that somebody at the very least calibrates the system.
Most of the system problems that we encountered could
be solved if this process was completed. In fact, as part
of our study we went back to each system and recommissioned them to measure the impact on performance.
Primarily, we followed the recommended calibration processes to adjust the daylight sensor and controller settings
to achieve adequate light levels at the critical work plane*
with minimum possible energy consumed. This process
aims to optimize the settings in Table 1. All that is needed
for the process is knowledge of the controls (including
locations), design illumination targets, and a light meter
for determining that design illumination is met.
Our study found that with these steps in place these
systems save substantial energy, and can be economically justified. More importantly, the study showed that
these key commissioning steps were critical to making
the technology justifiable.

What We Did
The Spaces
We began our study by locating buildings throughout
Minnesota and Wisconsin that used daylighting controls.
Of a larger sample set that included a range of building
types, we chose 20 spaces for in-depth study. The spaces
were chosen to be significantly different in orientation, usage, and perceived level of commissioning in an
attempt to achieve a diverse sampling of spaces.

Table 1 Six key items to be adjusted during daylighting control calibration.
SenSor locaTion

Sensor Should be Located Over a Workplane

SenSor orienTaTion

Sensor Should See Reflective, Representative Space

SenSor Shielding

Sensor Should Not Receive Direct Light

gain

Tune to Design Light Level + Lumen Depreciation

Fade raTe

Fade Rate Should be Long (~1 Minute)

deadband (iF STepped)

Deadband Should be Long (Several Minutes)

Data Collection
We collected data over three separate periods of time
to demonstrate the effect of commissioning. In Period
1, the control system was monitored in its as-found
state. In Period 2, the daylighting controls were disabled (other lighting controls remained functional)
such that the system would behave as if it never had
daylighting controls. Then, prior to Period 3, we completed a basic recommissioning of the system, with
the help of knowledgeable technicians. This process
included calibration of the key items discussed previously, and listed in Table 1.
In each space we installed continuous monitoring
equipment to collect several data points across all periods, beginning on Jan. 13, 2012, and concluding at the
end of Period 3 on July 10, 2012. For more information
regarding our monitored spaces and data points, refer to
our full report.4

Methodology and Analysis
Two different savings metrics were key outcomes of
this study: the energy savings from a typical daylighting
control system (measured in Period 1) and the energy
savings from a fully commissioned system (Period 3).
We calculated each metric for the luminaires controlled
by the daylighting control system. The measured lighting energy power was calculated using monitored
electrical current, along with spot measurements of
voltage and power factor. This calculation is represented in Figure 1, in which the energy usage of Period 1
and Period 3 is shown in yellow, while the energy savings is shown in orange. Recall that the energy savings
in Period 3 includes additional savings realized by full
commissioning.
But the primary goal of our study was not to look at the
architectural or lighting design impacts on daylighting

*The critical work plane is the location that receives the least daylight within the zone of controlled light.
Septem ber 2013

ashrae.org

ASHRAE JouRnAl

47



ASHRAE Journal - September 2013

Table of Contents for the Digital Edition of ASHRAE Journal - September 2013

Contents
ASHRAE Journal - September 2013 - Cover1
ASHRAE Journal - September 2013 - Cover2
ASHRAE Journal - September 2013 - 1
ASHRAE Journal - September 2013 - 2
ASHRAE Journal - September 2013 - Contents
ASHRAE Journal - September 2013 - 4
ASHRAE Journal - September 2013 - 5
ASHRAE Journal - September 2013 - 6
ASHRAE Journal - September 2013 - 7
ASHRAE Journal - September 2013 - 8
ASHRAE Journal - September 2013 - 9
ASHRAE Journal - September 2013 - 10
ASHRAE Journal - September 2013 - 11
ASHRAE Journal - September 2013 - 12
ASHRAE Journal - September 2013 - 13
ASHRAE Journal - September 2013 - 14
ASHRAE Journal - September 2013 - 15
ASHRAE Journal - September 2013 - 16
ASHRAE Journal - September 2013 - 17
ASHRAE Journal - September 2013 - 18
ASHRAE Journal - September 2013 - 19
ASHRAE Journal - September 2013 - 20
ASHRAE Journal - September 2013 - 21
ASHRAE Journal - September 2013 - 22
ASHRAE Journal - September 2013 - 23
ASHRAE Journal - September 2013 - 24
ASHRAE Journal - September 2013 - 25
ASHRAE Journal - September 2013 - 26
ASHRAE Journal - September 2013 - 27
ASHRAE Journal - September 2013 - 28
ASHRAE Journal - September 2013 - 29
ASHRAE Journal - September 2013 - 30
ASHRAE Journal - September 2013 - 31
ASHRAE Journal - September 2013 - 32
ASHRAE Journal - September 2013 - 33
ASHRAE Journal - September 2013 - 34
ASHRAE Journal - September 2013 - 35
ASHRAE Journal - September 2013 - 36
ASHRAE Journal - September 2013 - 37
ASHRAE Journal - September 2013 - 38
ASHRAE Journal - September 2013 - 39
ASHRAE Journal - September 2013 - 40
ASHRAE Journal - September 2013 - 41
ASHRAE Journal - September 2013 - 42
ASHRAE Journal - September 2013 - 43
ASHRAE Journal - September 2013 - 44
ASHRAE Journal - September 2013 - 45
ASHRAE Journal - September 2013 - 46
ASHRAE Journal - September 2013 - 47
ASHRAE Journal - September 2013 - 48
ASHRAE Journal - September 2013 - 49
ASHRAE Journal - September 2013 - 50
ASHRAE Journal - September 2013 - 51
ASHRAE Journal - September 2013 - 52
ASHRAE Journal - September 2013 - 53
ASHRAE Journal - September 2013 - 54
ASHRAE Journal - September 2013 - 55
ASHRAE Journal - September 2013 - 56
ASHRAE Journal - September 2013 - 57
ASHRAE Journal - September 2013 - 58
ASHRAE Journal - September 2013 - 59
ASHRAE Journal - September 2013 - 60
ASHRAE Journal - September 2013 - 61
ASHRAE Journal - September 2013 - 62
ASHRAE Journal - September 2013 - 63
ASHRAE Journal - September 2013 - 64
ASHRAE Journal - September 2013 - 65
ASHRAE Journal - September 2013 - 66
ASHRAE Journal - September 2013 - 67
ASHRAE Journal - September 2013 - 68
ASHRAE Journal - September 2013 - 69
ASHRAE Journal - September 2013 - 70
ASHRAE Journal - September 2013 - 71
ASHRAE Journal - September 2013 - 72
ASHRAE Journal - September 2013 - 73
ASHRAE Journal - September 2013 - 74
ASHRAE Journal - September 2013 - 75
ASHRAE Journal - September 2013 - 76
ASHRAE Journal - September 2013 - 77
ASHRAE Journal - September 2013 - 78
ASHRAE Journal - September 2013 - 79
ASHRAE Journal - September 2013 - 80
ASHRAE Journal - September 2013 - 81
ASHRAE Journal - September 2013 - 82
ASHRAE Journal - September 2013 - 83
ASHRAE Journal - September 2013 - 84
ASHRAE Journal - September 2013 - 85
ASHRAE Journal - September 2013 - 86
ASHRAE Journal - September 2013 - 87
ASHRAE Journal - September 2013 - 88
ASHRAE Journal - September 2013 - 89
ASHRAE Journal - September 2013 - 90
ASHRAE Journal - September 2013 - 91
ASHRAE Journal - September 2013 - 92
ASHRAE Journal - September 2013 - 93
ASHRAE Journal - September 2013 - 94
ASHRAE Journal - September 2013 - 95
ASHRAE Journal - September 2013 - 96
ASHRAE Journal - September 2013 - Cover3
ASHRAE Journal - September 2013 - Cover4
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_MCDEBX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WNYSQY
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XATVOD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_FJSHSS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_CCBZDS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XDEFVG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2023november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2023november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_VHGNBL
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WPKBNJ
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_UUVCDE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RTGDEW
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2023
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LKRFXS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_AZSOFG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ERCDBH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QWDFRV
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JHGVDF
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OPUYHG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SREIBM
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LRTGLK
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OKRFGH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2022november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2022november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TZSERA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LVRUIX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RPTVYZ
https://www.nxtbook.com/nxtbooks/ashrae/mini_pub_catalog
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XIYTGD
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2022
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RFGDOB
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PABXNU
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_REMKLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PICVBT
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_AOYTVW
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JQOPLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_IOYTBC
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SGAJJF
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_IGHYER
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PDRKLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2021november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2021november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XCODFR
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QSLFGO
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ILKVNM
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2021
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OPDJKD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_VJKSRY
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SDHUTC
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JPPKRR
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SDLTTH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_CKLLES
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SLDOX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_HJETUK
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OLUHGE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2020october
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2020october_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ZERDGH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QVMNEO
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RTPOKE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_BBATRE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_STUBMW
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TPEMPE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JNMKDS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_FBTTPA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WQMMNE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TVBRYN
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_showguide2020
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_KTUZMA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ABEDGD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201910
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201909
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2019septmeber_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2019september
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201908
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201907
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201906
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201905
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201904
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2019april
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201903
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2019march
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201902
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201901
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_showguide2019
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018december
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2018fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2018fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018october
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2018
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201810
https://www.nxtbook.com/nxtbooks/ashrae/ashraeinsights_201806
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201805
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201804
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201803
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201712
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201711
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201710
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2017fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2017fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201709
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201705
https://www.nxtbook.com/nxtbooks/ashrae/ashrae_meetinginsert_201610
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2016fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2016fall
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acrexindia
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2015summer_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2015summer
https://www.nxtbook.com/nxtbooks/amca/2014summer2
https://www.nxtbook.com/nxtbooks/amca/2014summer
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acma_2014summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201311
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201309
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acmasupp_2013fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201305
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201303
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2013winter
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201211
https://www.nxtbook.com/nxtbooks/ashrae/achr_expo_mexico2012
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201209
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201208_v3
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201208_v2
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2012summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201205
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201203
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2012winter
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201111_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201109_v2
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2011summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201105
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201103
https://www.nxtbookmedia.com