of a section of ductwork (Form 1, Page 45) and a VAV box
(Form 2, Page 46) meet contract requirements. As previously noted, the CxA will review these forms after the
contractor completes them. But the CxA also should personally observe either the installation or the contractor's
testing process. The CxA may even administer a test of
his/her own to verify proper installation.
Note that FIV test forms are developed by the CxA (not
the contractor) to use in performing the pre-functional
verifications that must be completed before equipment
and systems are up and running.
If any item on these forms is not properly installed
and/or checked off, the chance of that component not
operating properly increases. If a contractor discovers
items that don't conform to contract specifications, it's
the contractor's responsibility to enter those items into
the project issue log (the details of which will be discussed in the next article in this series).
The space limitations of this article do not permit us
to feature sample testing forms for other trades, but the
CxA will need to develop a set of FIV forms for each type
of equipment and every system.

Next Step: Operational Performance Tests
After installations are complete and all of the issues
revealed during the FIVs have been resolved, the OPTs
can begin. This set of pre-functional tests confirms that
all components and systems can be started up and are
run properly.
As with FIV tests, the forms need to list all of the items
for which the CxA must verify proper operation. As
with the FIVs, if any item on the form is not properly
completed, the likelihood of that component operating
improperly increases.
Form 3 (Page 48) is a sample OPT form used during
technical commissioning to verify that a VAV box is operating properly (a separate form should be completed for
each VAV box).

Dealing With Resistance
As can be expected, some people don't want to "buy
into" the technical commissioning process. For example,
a contractor may seem to display a solid understanding
of the proper installation and start-up methods during
their pre-installation meeting. They may say, "Let us
know if you find something wrong so we can fix it." On
the surface this seems like a reasonable attitude, but it
50

ASHRAE JouRnAl

ashrae.org

Apri l 2014

can lead to a lack of quality control on the contractor's
part: a situation in which the contractor races through
the installation and leaves the CxA to identify all of the
errors and oversights.
And while it's always best when everyone actively supports the technical commissioning process, it may be
necessary to add language to the contract that compensates the CxA in the event that redundant or extraneous
testing is required due to a contractor's lax attitude or
poor performance.
It's also important to mandate retesting in the event
that a high rate of errors is encountered. Certainly no
human enterprise is flawless, and "honest" mistakes
happen. But if it becomes apparent that a contractor has
falsified forms or approved items without testing, such
a situation should trigger an automatic retest of all components and systems related to that contractor. The cost
of additional retesting should be borne by the contactor
at fault-not the CxA or the owner.
When all pre-functional testing issues have been
resolved, you're ready to conduct the project's "final
exam": Functional performance testing, which is the
topic of the next article in this series.

Nothing Succeeds Like Success
Pre-functional tests are not complicated, but they are
time-consuming, which is the main reason they are
often ignored. However, savvy architects and contractors
have seen the light, and they understand that a proper
technical commissioning process greatly reduces the
number of call-backs.
I recall one project during which we literally pulled the
mechanical contractor through the PFT process, threatening back-charges if the tests were not done properly.
Although he completed the tests as we required, he
never stopped protesting and complaining about the
total waste of time and the complete foolishness of the
technical commissioning process.
A year later that project's architect called us and said,
"We're not sure what you did on this project, but we're
amazed-we've had only one call-back during the past
year. And that was just to fix some weather-stripping on
a door!"
Upon hearing that comment, the mechanical contactor
begrudgingly agreed, saying, "Well, I guess your technical commissioning process did work, because we got no
call-backs at all."



ASHRAE Journal - April 2014

Table of Contents for the Digital Edition of ASHRAE Journal - April 2014

ASHRAE Journal - April 2014
Contents
Commentary
Industry News
Letters
Meetings and Shows
Feature Articles
Lessons Learned from ASHRAE HQ Renovation
Current Trends for Health-Care Ventilation
Technical vs. Process Commissioning: Pre-Functional Testing
Building Sciences
Engineer's Notebook
Technology Award Case Study: Crime Lab Deconstruction
Refrigeration Applications
Technology Award Case Study: Designing for Sustainability
Data Centers
HVAC Applications
Energy Modeling
IAQ Applications
People
Special Products
Classified Advertising
Advertisers Index
ASHRAE Journal - April 2014 - ASHRAE Journal - April 2014
ASHRAE Journal - April 2014 - Cover2
ASHRAE Journal - April 2014 - 1
ASHRAE Journal - April 2014 - 2
ASHRAE Journal - April 2014 - Contents
ASHRAE Journal - April 2014 - Commentary
ASHRAE Journal - April 2014 - 5
ASHRAE Journal - April 2014 - Industry News
ASHRAE Journal - April 2014 - 7
ASHRAE Journal - April 2014 - Letters
ASHRAE Journal - April 2014 - 9
ASHRAE Journal - April 2014 - 10
ASHRAE Journal - April 2014 - 11
ASHRAE Journal - April 2014 - Meetings and Shows
ASHRAE Journal - April 2014 - 13
ASHRAE Journal - April 2014 - Lessons Learned from ASHRAE HQ Renovation
ASHRAE Journal - April 2014 - 15
ASHRAE Journal - April 2014 - 16
ASHRAE Journal - April 2014 - 17
ASHRAE Journal - April 2014 - 18
ASHRAE Journal - April 2014 - 19
ASHRAE Journal - April 2014 - 20
ASHRAE Journal - April 2014 - 21
ASHRAE Journal - April 2014 - 22
ASHRAE Journal - April 2014 - 23
ASHRAE Journal - April 2014 - 24
ASHRAE Journal - April 2014 - 25
ASHRAE Journal - April 2014 - 26
ASHRAE Journal - April 2014 - 27
ASHRAE Journal - April 2014 - 28
ASHRAE Journal - April 2014 - 29
ASHRAE Journal - April 2014 - 30
ASHRAE Journal - April 2014 - 31
ASHRAE Journal - April 2014 - Current Trends for Health-Care Ventilation
ASHRAE Journal - April 2014 - 33
ASHRAE Journal - April 2014 - 34
ASHRAE Journal - April 2014 - 35
ASHRAE Journal - April 2014 - 36
ASHRAE Journal - April 2014 - 37
ASHRAE Journal - April 2014 - 38
ASHRAE Journal - April 2014 - 39
ASHRAE Journal - April 2014 - 40
ASHRAE Journal - April 2014 - 41
ASHRAE Journal - April 2014 - 42
ASHRAE Journal - April 2014 - 43
ASHRAE Journal - April 2014 - Technical vs. Process Commissioning: Pre-Functional Testing
ASHRAE Journal - April 2014 - 45
ASHRAE Journal - April 2014 - 46
ASHRAE Journal - April 2014 - 47
ASHRAE Journal - April 2014 - 48
ASHRAE Journal - April 2014 - 49
ASHRAE Journal - April 2014 - 50
ASHRAE Journal - April 2014 - 51
ASHRAE Journal - April 2014 - Building Sciences
ASHRAE Journal - April 2014 - 53
ASHRAE Journal - April 2014 - 54
ASHRAE Journal - April 2014 - 55
ASHRAE Journal - April 2014 - 56
ASHRAE Journal - April 2014 - 57
ASHRAE Journal - April 2014 - Engineer's Notebook
ASHRAE Journal - April 2014 - 59
ASHRAE Journal - April 2014 - 60
ASHRAE Journal - April 2014 - 61
ASHRAE Journal - April 2014 - 62
ASHRAE Journal - April 2014 - 63
ASHRAE Journal - April 2014 - 64
ASHRAE Journal - April 2014 - 65
ASHRAE Journal - April 2014 - Technology Award Case Study: Crime Lab Deconstruction
ASHRAE Journal - April 2014 - 67
ASHRAE Journal - April 2014 - 68
ASHRAE Journal - April 2014 - 69
ASHRAE Journal - April 2014 - 70
ASHRAE Journal - April 2014 - 71
ASHRAE Journal - April 2014 - 72
ASHRAE Journal - April 2014 - 73
ASHRAE Journal - April 2014 - Refrigeration Applications
ASHRAE Journal - April 2014 - 75
ASHRAE Journal - April 2014 - Technology Award Case Study: Designing for Sustainability
ASHRAE Journal - April 2014 - 77
ASHRAE Journal - April 2014 - 78
ASHRAE Journal - April 2014 - 79
ASHRAE Journal - April 2014 - 80
ASHRAE Journal - April 2014 - 81
ASHRAE Journal - April 2014 - 82
ASHRAE Journal - April 2014 - 83
ASHRAE Journal - April 2014 - Data Centers
ASHRAE Journal - April 2014 - 85
ASHRAE Journal - April 2014 - 86
ASHRAE Journal - April 2014 - 87
ASHRAE Journal - April 2014 - 88
ASHRAE Journal - April 2014 - 89
ASHRAE Journal - April 2014 - HVAC Applications
ASHRAE Journal - April 2014 - 91
ASHRAE Journal - April 2014 - 92
ASHRAE Journal - April 2014 - Energy Modeling
ASHRAE Journal - April 2014 - IAQ Applications
ASHRAE Journal - April 2014 - 95
ASHRAE Journal - April 2014 - 96
ASHRAE Journal - April 2014 - 97
ASHRAE Journal - April 2014 - People
ASHRAE Journal - April 2014 - 99
ASHRAE Journal - April 2014 - 100
ASHRAE Journal - April 2014 - Special Products
ASHRAE Journal - April 2014 - 102
ASHRAE Journal - April 2014 - Classified Advertising
ASHRAE Journal - April 2014 - Advertisers Index
ASHRAE Journal - April 2014 - Cover3
ASHRAE Journal - April 2014 - Cover4
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_MCDEBX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WNYSQY
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XATVOD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_FJSHSS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_CCBZDS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XDEFVG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2023november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2023november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_VHGNBL
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WPKBNJ
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_UUVCDE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RTGDEW
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2023
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LKRFXS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_AZSOFG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ERCDBH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QWDFRV
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JHGVDF
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OPUYHG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SREIBM
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LRTGLK
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OKRFGH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2022november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2022november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TZSERA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LVRUIX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RPTVYZ
https://www.nxtbook.com/nxtbooks/ashrae/mini_pub_catalog
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XIYTGD
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2022
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RFGDOB
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PABXNU
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_REMKLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PICVBT
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_AOYTVW
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JQOPLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_IOYTBC
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SGAJJF
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_IGHYER
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PDRKLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2021november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2021november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XCODFR
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QSLFGO
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ILKVNM
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2021
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OPDJKD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_VJKSRY
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SDHUTC
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JPPKRR
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SDLTTH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_CKLLES
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SLDOX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_HJETUK
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OLUHGE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2020october
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2020october_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ZERDGH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QVMNEO
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RTPOKE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_BBATRE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_STUBMW
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TPEMPE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JNMKDS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_FBTTPA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WQMMNE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TVBRYN
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_showguide2020
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_KTUZMA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ABEDGD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201910
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201909
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2019septmeber_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2019september
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201908
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201907
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201906
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201905
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201904
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2019april
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201903
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2019march
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201902
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201901
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_showguide2019
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018december
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2018fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2018fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018october
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2018
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201810
https://www.nxtbook.com/nxtbooks/ashrae/ashraeinsights_201806
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201805
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201804
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201803
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201712
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201711
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201710
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2017fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2017fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201709
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201705
https://www.nxtbook.com/nxtbooks/ashrae/ashrae_meetinginsert_201610
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2016fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2016fall
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acrexindia
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2015summer_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2015summer
https://www.nxtbook.com/nxtbooks/amca/2014summer2
https://www.nxtbook.com/nxtbooks/amca/2014summer
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acma_2014summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201311
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201309
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acmasupp_2013fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201305
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201303
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2013winter
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201211
https://www.nxtbook.com/nxtbooks/ashrae/achr_expo_mexico2012
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201209
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201208_v3
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201208_v2
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2012summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201205
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201203
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2012winter
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201111_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201109_v2
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2011summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201105
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201103
https://www.nxtbookmedia.com