Chemical Processing - May 2008 - (Page 40) >> making it work making it work >> New workstations as well as the deep-well-injection/surge-tank Modicon PLC, with new controllers, I/O, workstations and networks. The interim workstations were slowly converted to pure DeltaVs. Cutover The cutover of the deep-well/surge PLC and the acetonitrile unit was next on the list. We performed a cold cutover because this work could be scheduled so it didn’t impede critical acrylonitrile production. The PLC had 148 points in the pump building’s main rack for injection logic and another 60 points for surge control in a coax-connected remote I/O rack in a distant control cabinet. The conversion of both could take no more than three days — the time it would take for the surge tanks to become full. Because space was available in the injection building, a new controller cabinet was installed near the PLC cabinet. Cutover required removing the PLC and then both retraining existing wiring and adding wiring from the old cabinet to the new. The old cabinet remains as a marshalling enclosure. The two-stage PLC conversion task was completed in three 14-hour days. Cold cutover of the acetonitrile unit was scheduled during a five-day outage that also included non-control work. The switch involved straightforward tearing out old cabinets, installing new cabinets, wiring up and checking out 292 I/O points, about 75% analog. Cutover took four days, plus a fifth day for tuning and tweaking. It was important that a few parameter indications, such as cyanide drum levels, be relayed to the control room during cutover. This was achieved by temporarily powering the new acetonitrile cabinets with an extension cord, limiting interruption of vital indications to only minutes. The acrylonitrile unit was cut over last and hot. The cutover of its 1,023 I/O points was spread over a two-month period ending in late November 2006. A team of two experienced contract electricians, a very knowledgeable and helpful operator, and me worked full-time on the project. The operator was essential for knowing how the control strategy and loops work — or should work — and for performing all of the necessary bypassing and hand-jacking of control valves. Although I know the process quite well, I’m a controls engineer, not a process engineer. On average, we converted and tuned three to five active control loops a day. Indication points usually were converted and rung out while waiting for loop tuning and process bumps to settle. The original tuning methods and parameters generally translated well. We made rough calculations of the tuning sets in the old controllers and then plugged these parameters into the new system. Many of the loops were also then tweaked using DeltaV supplied software. Our tuning upsets made operators nervous at www.chemicalprocessing.com Figure 1. Control room features both dual and quad-monitor DeltaV workstations. Old workstations were moved to the back wall. devices. The new PC workstations were mounted in semicircular console furniture (Figure 1) and connected in parallel with the existing consoles, which were moved against the back wall and remained live and operable until the new workstations were tested and proven to work with the existing controllers. To operators, the transition was essentially seamless; I don’t believe they ever used the old HMIs after the new workstations were up and running. The transition package seamlessly transferred the original DCS’ analog and discrete points plus loops into the interim workstations, as well as node operating status, configuration information and online tuning. No reconfiguration of old equipment was required. When connected in parallel, operating and tuning changes made from the package were automatically updated into the original system and vice versa. Very helpfully, the package added state-of-the-art event reporting, history collection, and enhanced alarming and diagnostics to the original controls. At operator request, the original graphics, including alarms, were replicated as closely as possible in the transition package. Graphics followed the guidelines of Engineering Equipment & Materials Users’ Association Publication 201 as to alarm management, colors, contrast, etc. Conversion from old consoles to new workstations took less than one week per control house. Phase 1 also included paralleling and then switching serial links from the old equipment directly to the project’s first new controller. This avoided two-step conversion (old to interim to new control) of 1,400 points. All Phase 1 work was accomplished hot with the plant running. No process trips occurred. Phase 2 replaced all the old controllers and I/O equipment, 40 • May 2008 http://www.chemicalprocessing.com
Table of Contents Feed for the Digital Edition of Chemical Processing - May 2008 From the Editor ChemicalProcessing.com Field Notes In Process Energy Saver Compliance Advisor WirelessHART signals a change at plants Avoid costly fabrication mistakes Watch out with variable speed pumping Hot cutover boosts control system migration Plant InSites Process Puzzler Equipment & Services Product Spotlight/Classifieds Ad Index End Point Chemical Processing - May 2008 Chemical Processing - May 2008 - (Page Cover1) Chemical Processing - May 2008 - (Page Cover2) Chemical Processing - May 2008 - (Page 3) Chemical Processing - May 2008 - (Page 4) Chemical Processing - May 2008 - (Page 5) Chemical Processing - May 2008 - (Page 6) Chemical Processing - May 2008 - (Page 7) Chemical Processing - May 2008 - (Page 8) Chemical Processing - May 2008 - From the Editor (Page 9) Chemical Processing - May 2008 - From the Editor (Page 10) Chemical Processing - May 2008 - ChemicalProcessing.com (Page 11) Chemical Processing - May 2008 - ChemicalProcessing.com (Page 12) Chemical Processing - May 2008 - Field Notes (Page 13) Chemical Processing - May 2008 - In Process (Page 14) Chemical Processing - May 2008 - In Process (Page 15) Chemical Processing - May 2008 - Energy Saver (Page 16) Chemical Processing - May 2008 - Compliance Advisor (Page 17) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 18) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 19) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 20) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 21) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 22) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 23) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 24) Chemical Processing - May 2008 - WirelessHART signals a change at plants (Page 25) Chemical Processing - May 2008 - Avoid costly fabrication mistakes (Page 26) Chemical Processing - May 2008 - Avoid costly fabrication mistakes (Page 27) Chemical Processing - May 2008 - Avoid costly fabrication mistakes (Page 28) Chemical Processing - May 2008 - Avoid costly fabrication mistakes (Page 29) Chemical Processing - May 2008 - Avoid costly fabrication mistakes (Page 30) Chemical Processing - May 2008 - Avoid costly fabrication mistakes (Page 31) Chemical Processing - May 2008 - Avoid costly fabrication mistakes (Page 32) Chemical Processing - May 2008 - Watch out with variable speed pumping (Page 33) Chemical Processing - May 2008 - Watch out with variable speed pumping (Page 34) Chemical Processing - May 2008 - Watch out with variable speed pumping (Page 35) Chemical Processing - May 2008 - Watch out with variable speed pumping (Page 36) Chemical Processing - May 2008 - Watch out with variable speed pumping (Page 37) Chemical Processing - May 2008 - Watch out with variable speed pumping (Page 38) Chemical Processing - May 2008 - Hot cutover boosts control system migration (Page 39) Chemical Processing - May 2008 - Hot cutover boosts control system migration (Page 40) Chemical Processing - May 2008 - Hot cutover boosts control system migration (Page 41) Chemical Processing - May 2008 - Hot cutover boosts control system migration (Page 42) Chemical Processing - May 2008 - Process Puzzler (Page 43) Chemical Processing - May 2008 - Plant InSites (Page 44) Chemical Processing - May 2008 - Equipment & Services (Page 45) Chemical Processing - May 2008 - Product Spotlight/Classifieds (Page 46) Chemical Processing - May 2008 - Product Spotlight/Classifieds (Page 47) Chemical Processing - May 2008 - Product Spotlight/Classifieds (Page 48) Chemical Processing - May 2008 - Ad Index (Page 49) Chemical Processing - May 2008 - End Point (Page 50) Chemical Processing - May 2008 - End Point (Page Cover3) Chemical Processing - May 2008 - End Point (Page Cover4)
For optimal viewing of this digital publication, please enable JavaScript and then refresh the page. If you would like to try to load the digital publication without using Flash Player detection, please click here.