Consulting-Specifying Engineer - August 2007 - (Page 42) How To B E AT T H E C O D E S Ice-storage systems BY PAUL VALENTA, North American sales manager, CALMAC Manufacturing, Fair Lawn, N.J. C onsulting engineers must provide cooling designs that will work in a variety of conditions from low loads to unexpected heavy loads on peak design days. Therefore, safety factors become a consideration of risk, first cost and operating cost. Is there a better choice than to install a 20% larger chiller for a facility to occasionally meet unusually high or unexpected loads? That extra chiller capacity with its larger support equipment can result in lower energy efficiency and increased maintenance costs with poor return-on-investment (ROI) because oversized cooling systems that quickly cycle on and Instead of adding 20% chiller capacity to a design day building peak load, reduce chiller capacity by at least 20% and add ice storage for safety factor. off to meet set points might not dehumidify the air properly. In addition to operational inefficiency, poor indoor air quality can be a side effect of oversizing. Is there a better choice? Consider a building that has a peak cooling requirement of 1,000 tons on a design day. One 1,000-ton chiller would do the job on most days, but this choice provides no safety factor for days warmer than ASHRAE design—days with unexpected loads—or for future growth. Additionally, should the chiller fail, no cooling would be available. Designing the system instead with two 500-ton chillers would not provide extra safety factor capacity, but would provide half capacity should one chiller fail. The U.S. General Services Administration directs engineers to design three equal-size chillers that total 120% of the buildings peak load. In this case, three 400-ton chillers would be required to provide 20% safety factor and 80% capacity should one chiller be unavailable. A cooling load profile from a popular HVAC modeling program (see Table 1) for a 1,000-ton building in Chicago shows that 87% of the time the load is less than 800 tons, or 66% of the recommended GSA installed chiller capacity. Seventy-six percent of the time the cooling load is less than 700 tons, or just under 60% of the GSA chiller installed capacity. The investment in 200 tons of safety factor capacity, including the larger chillers, cooling towers, fans, pumps and electrical equipment, results in a higher cost and connected electrical load for capacity that is seldom used and has minimal ROI. Should one chiller become unavailable, the conventional selection of three 400-ton chillers provides 80% capacity. This is a reasonable operational risk because most operating hours have capacities less than 80% design-day load. Figure 1 shows a cooling load profile for a 1,000-ton design day load profile for an office building. The conventional scenario would be to install three 400-ton chillers to supply safety factor and redundancy. Figure 1 also shows the chiller potential over the required cooling load profile the building requires. Now compare the conventional-chiller-only system with a partial-ice-storage system, keeping in mind that safety factor and redundancy are requirements of the ice storage system as well. For this example, the third chiller or “safety factor chiller” is replaced with ice storage. Two 400-ton ice making chillers and 3,900-ton hours of storage are selected for the system. The ice storage provides the safety factor and redundancy just as the third chiller did in the conventional design. Cooling towers and all chiller support equipment are now sized for 800 tons. The potential load profiles are compared in Figure 1. Notice that the ice storage system is capable of a larger peak capacity than the conventional system if needed. In this case the safety factor is comparable. 42 Consulting-Specifying Engineer • AUGUST, 2007
Table of Contents Feed for the Digital Edition of Consulting-Specifying Engineer - August 2007 Contents M/E Roundtable Giants 100 Pullout Poster Giants Stand Tall: CSE Giants 100 Report Electrical Design for Tall Buildings HVAC and Fire Safety for Elevator Systems How to Beat the Codes GAS Technology Supplement Recovering Waste Heat from Boilers New Applications for Tankless Water Heating Systmes Techniques Improve for Powder Coating MDF New Tools Available for Heat Treating Steel Direct Drive Engines Consulting-Specifying Engineer - August 2007 Consulting-Specifying Engineer - August 2007 - (Page Cover1) Consulting-Specifying Engineer - August 2007 - (Page Cover2) Consulting-Specifying Engineer - August 2007 - (Page 1) Consulting-Specifying Engineer - August 2007 - (Page 2) Consulting-Specifying Engineer - August 2007 - Contents (Page 3) Consulting-Specifying Engineer - August 2007 - Contents (Page 4) Consulting-Specifying Engineer - August 2007 - Contents (Page 5) Consulting-Specifying Engineer - August 2007 - Contents (Page 6) Consulting-Specifying Engineer - August 2007 - Contents (Page 7) Consulting-Specifying Engineer - August 2007 - Contents (Page 8) Consulting-Specifying Engineer - August 2007 - Contents (Page 9) Consulting-Specifying Engineer - August 2007 - Contents (Page 10) Consulting-Specifying Engineer - August 2007 - Contents (Page 11) Consulting-Specifying Engineer - August 2007 - Contents (Page 12) Consulting-Specifying Engineer - August 2007 - Contents (Page 13) Consulting-Specifying Engineer - August 2007 - Contents (Page 14) Consulting-Specifying Engineer - August 2007 - Contents (Page 15) Consulting-Specifying Engineer - August 2007 - Contents (Page 16) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 17) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 18) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 19) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 20) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 21) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 22) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 23) Consulting-Specifying Engineer - August 2007 - M/E Roundtable (Page 24) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24A) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24B) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24C) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24D) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24E) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24F) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24G) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24H) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24I) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24J) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24K) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24L) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24M) Consulting-Specifying Engineer - August 2007 - Giants 100 Pullout Poster (Page 24N) Consulting-Specifying Engineer - August 2007 - Giants Stand Tall: CSE Giants 100 Report (Page 25) Consulting-Specifying Engineer - August 2007 - Giants Stand Tall: CSE Giants 100 Report (Page 26) Consulting-Specifying Engineer - August 2007 - Giants Stand Tall: CSE Giants 100 Report (Page 27) Consulting-Specifying Engineer - August 2007 - Giants Stand Tall: CSE Giants 100 Report (Page 28) Consulting-Specifying Engineer - August 2007 - Giants Stand Tall: CSE Giants 100 Report (Page 29) Consulting-Specifying Engineer - August 2007 - Electrical Design for Tall Buildings (Page 30) Consulting-Specifying Engineer - August 2007 - Electrical Design for Tall Buildings (Page 31) Consulting-Specifying Engineer - August 2007 - Electrical Design for Tall Buildings (Page 32) Consulting-Specifying Engineer - August 2007 - Electrical Design for Tall Buildings (Page 33) Consulting-Specifying Engineer - August 2007 - Electrical Design for Tall Buildings (Page 34) Consulting-Specifying Engineer - August 2007 - Electrical Design for Tall Buildings (Page 35) Consulting-Specifying Engineer - August 2007 - HVAC and Fire Safety for Elevator Systems (Page 36) Consulting-Specifying Engineer - August 2007 - HVAC and Fire Safety for Elevator Systems (Page 37) Consulting-Specifying Engineer - August 2007 - HVAC and Fire Safety for Elevator Systems (Page 38) Consulting-Specifying Engineer - August 2007 - HVAC and Fire Safety for Elevator Systems (Page 39) Consulting-Specifying Engineer - August 2007 - HVAC and Fire Safety for Elevator Systems (Page 40) Consulting-Specifying Engineer - August 2007 - HVAC and Fire Safety for Elevator Systems (Page 41) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 42) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 43) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 44) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 45) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 46) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 47) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 48) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 49) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 50) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 51) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 52) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 53) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 54) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 55) Consulting-Specifying Engineer - August 2007 - How to Beat the Codes (Page 56) Consulting-Specifying Engineer - August 2007 - GAS Technology Supplement (Page A1) Consulting-Specifying Engineer - August 2007 - Recovering Waste Heat from Boilers (Page A2) Consulting-Specifying Engineer - August 2007 - Recovering Waste Heat from Boilers (Page A3) Consulting-Specifying Engineer - August 2007 - Recovering Waste Heat from Boilers (Page A4) Consulting-Specifying Engineer - August 2007 - New Applications for Tankless Water Heating Systmes (Page A5) Consulting-Specifying Engineer - August 2007 - Techniques Improve for Powder Coating MDF (Page A6) Consulting-Specifying Engineer - August 2007 - Techniques Improve for Powder Coating MDF (Page A7) Consulting-Specifying Engineer - August 2007 - New Tools Available for Heat Treating Steel (Page A8) Consulting-Specifying Engineer - August 2007 - New Tools Available for Heat Treating Steel (Page A9) Consulting-Specifying Engineer - August 2007 - Direct Drive Engines (Page A10) Consulting-Specifying Engineer - August 2007 - Direct Drive Engines (Page A11) Consulting-Specifying Engineer - August 2007 - Direct Drive Engines (Page A12) Consulting-Specifying Engineer - August 2007 - Direct Drive Engines (Page Cover3) Consulting-Specifying Engineer - August 2007 - Direct Drive Engines (Page Cover4)
For optimal viewing of this digital publication, please enable JavaScript and then refresh the page. If you would like to try to load the digital publication without using Flash Player detection, please click here.