Consulting-Specifying Engineer - September 2008 - (Page 34) \\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\ gain experience with the systems. It is also imperative that periodic testing and/or re-commissioning of an existing electrical system be performed to help ensure that it continues to operate per the design intent. Electrical commissioning The following is an example of how these phases were implemented to successfully commission the electrical systems for a critical data center in North Carolina. The owner’s pre-design requirement was for a data center facility that had a concurrently maintainable infrastructure with fault-tolerant critical systems. During this phase the owner also determined that all critical electrical systems would be factory tested and then validated through on-site testing. Because the commissioning agent was involved in the pre-design discussions, he was aware of the owner’s expectations. The data center’s design was based on an isolated redundant-type system with a primary distribution system for each section of the data center, and a redundant distribution system to back up the primary systems. Many crucial decisions made during the design phase impacted the operation of the facility and commissioning. For example, the owner preferred to have two sources of power to this facility, but only one medium-voltage source was available in the area. The client decided to spend extra money in redundant backup systems. Having knowledge of key design decisions helped the commissioning agent to develop the validation testing procedures. Commissioning factors also affected the design of the distribution system. The owner required that a portion of the data center be live, serving critical load before the entire facility could be completed. The redundant systems were installed first in a section of the existing building, and the existing service was used to temporarily serve the data center until the new service and UPS plant were constructed. Once the new primary systems were installed, they had to be tested and commissioned around a live data center. Developing the commissioning plan early in the project was vital in providing guidance on how to design and build the facility so that the later phases of construction could be tested and validated without affecting the portion that was already online. During the construction phase, all parties reviewed equipment submittals, and all critical electrical equipment was factory witness tested. Due to the complexity of the electrical systems, the manufacturer developed a simulator for testing. Through the use of the simulator, various failure scenarios were tested and the control sequence was modified so that the system operated per the requirements of the owner. Commissioning procedures and checklists were written. In addition, the arc flash analysis and coordination study were reviewed, and all protection device trip settings were verified. The operational phase was split into multiple sections because of the phased construction. In each phase of construction, the individual pieces of equipment were tested; the discrete systems required to bring that particular phase online were then tested. Once all phases of construction were completed, the entire facility was turned over for integrated systems testing, where a “black start” test was conducted with multiple failure scenarios (loss of generator, loss of primary backup system, UPS failure, etc.). Problems did occur in each phase of testing (defective breakers, interaction of systems during a failure, coordination issues with inrush, etc.). All of these problems were corrected and retested until the system operated per the design intent. The month after the facility was fully commissioned, the owner started a worldwide migration to the new facility. Halfway through the migration, a snake crawled across two phases of a 25 kV utility service switch and caused a fault that interrupted service to the facility. During the utility power outage, one of the standby systems tripped and went offline. The electrical system reacted properly and transferred the critical load to the redundant standby power system. Because the electrical system was commissioned, it operated as designed and the owner never lost power to the critical load. The owner estimated that the cost to recover from losing power to the critical load during the migration would have been $5 million. Two key tasks of commissioning electrical systems are: • Defining the value to the client • Becoming involved early in the design process. The more complex and critical the electrical system becomes and the greater the exposure to risk involved with loss of power, the more crucial it is to commission the system and verify that it will operate as designed. Kutsmeda is engineering design principal/assistant electrical chief with KlingStubbins, Philadelphia. For more than 15 years, he has been responsible for the engineering, design, and commissioning of electrical power and lighting distribution systems. His project experience includes 7x24 mission critical facilities, highly specialized research and development buildings, and large-scale technology projects. \\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\ Testing references References for inspecting and testing electrical distribution equipment are: • ANSI C37.50—Low-Voltage AC Power Circuit Breakers Used in Enclosures—Test Procedures • IEEE 450—Recommended Practice for Maintenance, Testing and Replacement of Vented Lead Acid Batteries for Stationary Applications • IEEE 1188—Recommended Practice for Maintenance, Testing and Replacement of Valve Regulated Lead Acid Batteries for Stationary Applications • NEMA AB4—Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications • NETA ATS—Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems • NFPA 70B—Recommended Practice for Electrical Equipment Maintenance • NFPA 70C—National Electrical Code • NFPA 70E—Standard for Electrical Safety in the Workplace • NFPA 101—Life Safety Code • NFPA 110—Standard for Emergency and Standby Power Systems • NFPA 111—Standard for Stored Energy Emergency and Standby Power Systems • OSHA 34 Consulting-Specifying Engineer • SEPTEMBER 2008
Table of Contents Feed for the Digital Edition of Consulting-Specifying Engineer - September 2008 Consulting-Specifying Engineer - September 2008 Contents Viewpoint Letters News M/ERoundtable Selecting Appropriate Egress Strategies Commissioning On-Site Electrical Systems Mentoring Control Engineers and Technicians Casting Call for Cx Case Study New Products Equipment Lifecycles Advertiser Index Green Space Consulting-Specifying Engineer - September 2008 Consulting-Specifying Engineer - September 2008 - (Page Intro) Consulting-Specifying Engineer - September 2008 - Consulting-Specifying Engineer - September 2008 (Page Cover1) Consulting-Specifying Engineer - September 2008 - Consulting-Specifying Engineer - September 2008 (Page Cover2) Consulting-Specifying Engineer - September 2008 - Consulting-Specifying Engineer - September 2008 (Page 1) Consulting-Specifying Engineer - September 2008 - Consulting-Specifying Engineer - September 2008 (Page 2) Consulting-Specifying Engineer - September 2008 - Contents (Page 3) Consulting-Specifying Engineer - September 2008 - Contents (Page 4) Consulting-Specifying Engineer - September 2008 - Contents (Page 5) Consulting-Specifying Engineer - September 2008 - Contents (Page 6) Consulting-Specifying Engineer - September 2008 - Viewpoint (Page 7) Consulting-Specifying Engineer - September 2008 - Letters (Page 8) Consulting-Specifying Engineer - September 2008 - Letters (Page 9) Consulting-Specifying Engineer - September 2008 - News (Page 10) Consulting-Specifying Engineer - September 2008 - News (Page 11) Consulting-Specifying Engineer - September 2008 - News (Page 12) Consulting-Specifying Engineer - September 2008 - News (Page 13) Consulting-Specifying Engineer - September 2008 - M/ERoundtable (Page 14) Consulting-Specifying Engineer - September 2008 - M/ERoundtable (Page 15) Consulting-Specifying Engineer - September 2008 - M/ERoundtable (Page 16) Consulting-Specifying Engineer - September 2008 - M/ERoundtable (Page 17) Consulting-Specifying Engineer - September 2008 - M/ERoundtable (Page 18) Consulting-Specifying Engineer - September 2008 - M/ERoundtable (Page 19) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 20) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 21) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 22) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 23) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 24) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 25) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 26) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 27) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 28) Consulting-Specifying Engineer - September 2008 - Selecting Appropriate Egress Strategies (Page 29) Consulting-Specifying Engineer - September 2008 - Commissioning On-Site Electrical Systems (Page 30) Consulting-Specifying Engineer - September 2008 - Commissioning On-Site Electrical Systems (Page 31) Consulting-Specifying Engineer - September 2008 - Commissioning On-Site Electrical Systems (Page 32) Consulting-Specifying Engineer - September 2008 - Commissioning On-Site Electrical Systems (Page 33) Consulting-Specifying Engineer - September 2008 - Commissioning On-Site Electrical Systems (Page 34) Consulting-Specifying Engineer - September 2008 - Commissioning On-Site Electrical Systems (Page 35) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 36) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 37) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 38) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 39) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 40) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 41) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 42) Consulting-Specifying Engineer - September 2008 - Mentoring Control Engineers and Technicians (Page 43) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 44) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 45) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 46) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 47) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 48) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 49) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 50) Consulting-Specifying Engineer - September 2008 - Casting Call for Cx (Page 51) Consulting-Specifying Engineer - September 2008 - Case Study (Page 52) Consulting-Specifying Engineer - September 2008 - Case Study (Page 53) Consulting-Specifying Engineer - September 2008 - New Products (Page 54) Consulting-Specifying Engineer - September 2008 - New Products (Page 55) Consulting-Specifying Engineer - September 2008 - New Products (Page 56) Consulting-Specifying Engineer - September 2008 - New Products (Page 57) Consulting-Specifying Engineer - September 2008 - New Products (Page 58) Consulting-Specifying Engineer - September 2008 - New Products (Page 59) Consulting-Specifying Engineer - September 2008 - New Products (Page 60) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 61) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 62) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 63) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 64) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 65) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 66) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 67) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 68) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 69) Consulting-Specifying Engineer - September 2008 - Equipment Lifecycles (Page 70) Consulting-Specifying Engineer - September 2008 - Advertiser Index (Page 71) Consulting-Specifying Engineer - September 2008 - Green Space (Page 72) Consulting-Specifying Engineer - September 2008 - Green Space (Page Cover3) Consulting-Specifying Engineer - September 2008 - Green Space (Page Cover4)
For optimal viewing of this digital publication, please enable JavaScript and then refresh the page. If you would like to try to load the digital publication without using Flash Player detection, please click here.