Consulting-Specifying Engineer - November 2007 - (Page 24) 1,500 kW ESB 277/480V, 3Ø, 4W 2,500 1,200 400 ATS-EQ 1,200 ATS-CR 1,200 Figure 3 Panel serving two automatic transfer switches. adjustable. Here the engineer must carefully adjust the settings to achieve satisfactory coordination. The NEC does not clearly define what must be selectively coordinate. Therefore, it is up to the engineer to work with the local AHJ to determine an interpretation of what is selective coordination and at what the requirements will be. In Florida healthcare, the local AHJ has required selective coordination plots, signed and sealed by the engineer of record, for years. The requirements for selective coordination have evolved through the years in this region and currently require selective coordination from 0.10 s on. In order to understand the protection of the generator and the selective coordination of the generator, some basic understanding of time-current curves is required. Time-current curves are log graphs that represent the tripping time versus the current of breakers. They also are used to demonstrate the damage curve for generators, transformers, motors and wires, and to evaluate the fault contribution from a generator, or the inrush seen from a transformer. To do a complete selective coordination study, all of the above items must be considered. For a generator the two important components are the damage curve and the decrement curve. The damage curve (i.e. overload curve or withstand curve) is a measure of current from which the generator will be damaged. The decrement curve, as stated above, is a measure of the fault current produced by the generator. In the event that the generator faults, we want the breaker closest to the fault to trip and protect the system. The fault current must be sufficient to allow the breaker to trip. A standard generator cannot maintain fault current for long, so standard practice is to use a permanent magnet generator. This generator will maintain approximately 300% of the rated current for approximately 10 s, long enough for the downstream breakers to trip and protect the system. At approximately 10 s, the decrement (fault) curve will intersect with the damage curve for the generator. The selective coordination for the emergency power system must protect the generator, but allow the downstream breakers to trip. Figure 3 shows a panel serving two ATS. Panel ESB is the parallel switchboard (only one generator is shown) that serves a transfer switch ATS-EQ via a 1,200-amp breaker. This board is fed by several 1,500-kW generators with 2,500-amp breakers protecting each. Selective coordination requires that the ATS-EQ breaker trip before the GEN breaker. But if the fault is greater than both breakers, what will happen? We want to avoid a situation where a fault will take a generator offline before it takes the faulted branch of line. In Figure 3, we don’t want a fault in ATS-EQ to take the generator offline because it will remove the power for ATS-CR. This is not selective coordination. The goal is simple: design the protection that allows the downstream breakers to trip before the generator breaker trips. The generator breaker in Figure 4 is set to the right of the decrement curve from 0 s through 2 s, and crosses to the left of the decrement curve before damage to the engine occurs. Remember, the decrement curve is the fault output for the generator. It is important to note that many generator controllers have internal overcurrent protection that will take the generator off-line as well. Make sure you work with the manufacturer to confirm you have a complete selective coordination system. Emergency system design is a critical first step toward the proper operation of today’s healthcare facilities. Identifying the issues and addressing the challenges one at a time, we will be able to provide a safe and reliable emergency system, and do our part toward enhancing patient safety. 1,000 Current in Amperes GEN-0001 EDP-CB6 Trip 1200 A Settings Phase LTPU/LTD (A 0.4-1.0 x S) 1 (1200A); 0.5 STPU (1.5-10 x LTPU) 4 (4800A) STD (0-0.4) 0.1(I^2 T Out) INST (2-15 x S) 2 (1600A) Damage Curve 100 Decrement Curve 10 Time in Seconds GEN-MCB Trip 2500 A Settings Phase L LTPU/LTD (A 0.4-1.0 x S) 1 (2500A); 0.5 L STPU (1.5-10 x LTPU) 10 (25000A) STD (INST-0.4) 0.4(I^2 T Out) INST (2-15 x S) 12 (30000A) 1 0.10 0.01 10 100 1K 10K 100K Figure 4 Time current curve showing genset decrement curve. 24 Consulting-Specifying Engineer • NOVEMBER 2007
Table of Contents Feed for the Digital Edition of Consulting-Specifying Engineer - November 2007 Consulting-Specifying Engineer Contents Editor's Viewpoint Letters In The News M/E Roundtable Emergency Power for Healthcare 2007 Products of the Year Industrial-strength Lighting Hazardous HVAC Codes and Standards Management Report Jobs/Classifieds Specifier's Notebook On-Peak Performance Contents Best Battery Selector in Engine Starting Applications NEC 708: Practical Impact on Backup Power Systems Protecting Power: Specifying Outdoor Generator Enclosures Investing in Backup Power Systems Coes, Consultants, Manufacturers, and Standby Power Systems Consulting-Specifying Engineer - November 2007 Consulting-Specifying Engineer - November 2007 - (Page Intro) Consulting-Specifying Engineer - November 2007 - Consulting-Specifying Engineer (Page Cover1) Consulting-Specifying Engineer - November 2007 - Consulting-Specifying Engineer (Page Cover2) Consulting-Specifying Engineer - November 2007 - Consulting-Specifying Engineer (Page 1) Consulting-Specifying Engineer - November 2007 - Consulting-Specifying Engineer (Page 2) Consulting-Specifying Engineer - November 2007 - Contents (Page 3) Consulting-Specifying Engineer - November 2007 - Contents (Page 4) Consulting-Specifying Engineer - November 2007 - Editor's Viewpoint (Page 5) Consulting-Specifying Engineer - November 2007 - Editor's Viewpoint (Page 6) Consulting-Specifying Engineer - November 2007 - Letters (Page 7) Consulting-Specifying Engineer - November 2007 - Letters (Page 8) Consulting-Specifying Engineer - November 2007 - In The News (Page 9) Consulting-Specifying Engineer - November 2007 - In The News (Page 10) Consulting-Specifying Engineer - November 2007 - M/E Roundtable (Page 11) Consulting-Specifying Engineer - November 2007 - M/E Roundtable (Page 12) Consulting-Specifying Engineer - November 2007 - M/E Roundtable (Page 13) Consulting-Specifying Engineer - November 2007 - M/E Roundtable (Page 14) Consulting-Specifying Engineer - November 2007 - M/E Roundtable (Page 15) Consulting-Specifying Engineer - November 2007 - M/E Roundtable (Page 16) Consulting-Specifying Engineer - November 2007 - M/E Roundtable (Page 17) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 18) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 19) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 20) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 21) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 22) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 23) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 24) Consulting-Specifying Engineer - November 2007 - Emergency Power for Healthcare (Page 25) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 26) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 27) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 28) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 29) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 30) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 31) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 32) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 33) Consulting-Specifying Engineer - November 2007 - 2007 Products of the Year (Page 34) Consulting-Specifying Engineer - November 2007 - Industrial-strength Lighting (Page 35) Consulting-Specifying Engineer - November 2007 - Industrial-strength Lighting (Page 36) Consulting-Specifying Engineer - November 2007 - Industrial-strength Lighting (Page 37) Consulting-Specifying Engineer - November 2007 - Industrial-strength Lighting (Page 38) Consulting-Specifying Engineer - November 2007 - Industrial-strength Lighting (Page 39) Consulting-Specifying Engineer - November 2007 - Industrial-strength Lighting (Page 40) Consulting-Specifying Engineer - November 2007 - Hazardous HVAC (Page 41) Consulting-Specifying Engineer - November 2007 - Hazardous HVAC (Page 42) Consulting-Specifying Engineer - November 2007 - Hazardous HVAC (Page 43) Consulting-Specifying Engineer - November 2007 - Hazardous HVAC (Page 44) Consulting-Specifying Engineer - November 2007 - Hazardous HVAC (Page 45) Consulting-Specifying Engineer - November 2007 - Hazardous HVAC (Page 46) Consulting-Specifying Engineer - November 2007 - Codes and Standards (Page 47) Consulting-Specifying Engineer - November 2007 - Codes and Standards (Page 48) Consulting-Specifying Engineer - November 2007 - Codes and Standards (Page 49) Consulting-Specifying Engineer - November 2007 - Codes and Standards (Page 50) Consulting-Specifying Engineer - November 2007 - Management Report (Page 51) Consulting-Specifying Engineer - November 2007 - Management Report (Page 52) Consulting-Specifying Engineer - November 2007 - Jobs/Classifieds (Page 53) Consulting-Specifying Engineer - November 2007 - Jobs/Classifieds (Page 54) Consulting-Specifying Engineer - November 2007 - Jobs/Classifieds (Page 55) Consulting-Specifying Engineer - November 2007 - Jobs/Classifieds (Page 56) Consulting-Specifying Engineer - November 2007 - Jobs/Classifieds (Page 57) Consulting-Specifying Engineer - November 2007 - Specifier's Notebook (Page 58) Consulting-Specifying Engineer - November 2007 - Specifier's Notebook (Page Cover3) Consulting-Specifying Engineer - November 2007 - Specifier's Notebook (Page Cover4) Consulting-Specifying Engineer - November 2007 - On-Peak Performance (Page S1) Consulting-Specifying Engineer - November 2007 - On-Peak Performance (Page S2) Consulting-Specifying Engineer - November 2007 - Contents (Page S3) Consulting-Specifying Engineer - November 2007 - Best Battery Selector in Engine Starting Applications (Page S4) Consulting-Specifying Engineer - November 2007 - Best Battery Selector in Engine Starting Applications (Page S5) Consulting-Specifying Engineer - November 2007 - Best Battery Selector in Engine Starting Applications (Page S6) Consulting-Specifying Engineer - November 2007 - Best Battery Selector in Engine Starting Applications (Page S7) Consulting-Specifying Engineer - November 2007 - Best Battery Selector in Engine Starting Applications (Page S8) Consulting-Specifying Engineer - November 2007 - Best Battery Selector in Engine Starting Applications (Page S9) Consulting-Specifying Engineer - November 2007 - Best Battery Selector in Engine Starting Applications (Page S10) Consulting-Specifying Engineer - November 2007 - NEC 708: Practical Impact on Backup Power Systems (Page S11) Consulting-Specifying Engineer - November 2007 - NEC 708: Practical Impact on Backup Power Systems (Page S12) Consulting-Specifying Engineer - November 2007 - NEC 708: Practical Impact on Backup Power Systems (Page S13) Consulting-Specifying Engineer - November 2007 - NEC 708: Practical Impact on Backup Power Systems (Page S14) Consulting-Specifying Engineer - November 2007 - NEC 708: Practical Impact on Backup Power Systems (Page S15) Consulting-Specifying Engineer - November 2007 - NEC 708: Practical Impact on Backup Power Systems (Page S16) Consulting-Specifying Engineer - November 2007 - NEC 708: Practical Impact on Backup Power Systems (Page S17) Consulting-Specifying Engineer - November 2007 - Protecting Power: Specifying Outdoor Generator Enclosures (Page S18) Consulting-Specifying Engineer - November 2007 - Protecting Power: Specifying Outdoor Generator Enclosures (Page S19) Consulting-Specifying Engineer - November 2007 - Protecting Power: Specifying Outdoor Generator Enclosures (Page S20) Consulting-Specifying Engineer - November 2007 - Protecting Power: Specifying Outdoor Generator Enclosures (Page S21) Consulting-Specifying Engineer - November 2007 - Protecting Power: Specifying Outdoor Generator Enclosures (Page S22) Consulting-Specifying Engineer - November 2007 - Investing in Backup Power Systems (Page S23) Consulting-Specifying Engineer - November 2007 - Investing in Backup Power Systems (Page S24) Consulting-Specifying Engineer - November 2007 - Investing in Backup Power Systems (Page S25) Consulting-Specifying Engineer - November 2007 - Investing in Backup Power Systems (Page S26) Consulting-Specifying Engineer - November 2007 - Investing in Backup Power Systems (Page S27) Consulting-Specifying Engineer - November 2007 - Investing in Backup Power Systems (Page S28) Consulting-Specifying Engineer - November 2007 - Coes, Consultants, Manufacturers, and Standby Power Systems (Page S29) Consulting-Specifying Engineer - November 2007 - Coes, Consultants, Manufacturers, and Standby Power Systems (Page S30) Consulting-Specifying Engineer - November 2007 - Coes, Consultants, Manufacturers, and Standby Power Systems (Page S31) Consulting-Specifying Engineer - November 2007 - Coes, Consultants, Manufacturers, and Standby Power Systems (Page S32)
For optimal viewing of this digital publication, please enable JavaScript and then refresh the page. If you would like to try to load the digital publication without using Flash Player detection, please click here.