Commercial Architecture June 2019 - 20
▲
FEATURE
| building technology
Laser scans were used to create an
as-built 3D model, in this case the
concourse, which was then updated
continuously with new data throughout
the years of construction to track productivity, completion, and quality, and
plan for future work.
Wrigley Field. The construction sequence began with
installation. There was never room to have more than
ic marquee sign was reconstructed and rewired, and
retaining-wall installation and load-bearing elements
two or three days of steel ready for installation.
the caretaker's house was preserved to comply with
that carried the future structure. The next steps
When the steel arrived, it was taken off the truck
landmark requirements and moved across the street
involved constructing floor slabs on grade and mining
with a crane, set in place and shored up from below.
while a new foundation was installed and then moved
out the earth below. It provided an added benefit of
This just-in-time prefabrication and delivery process
back to its original location.
simultaneously erecting the structure going up. This
had a tremendous impact on expediting the schedule
Every phase of the project posed significant engi-
process saved money and had the least impact on the
and reducing costs. For the steel-erection company,
neering and construction challenges. However, inno-
adjacent stadium so the baseball season would be
that meant, nearly every day, receiving and installing
vative thinking and a singular focus on delivering the
uninterrupted.
large pieces of structural steel with tight tolerances.
best-possible result from the entire team brought this
Overall, 880 tons of steel were installed in just the out-
renovation to fruition. The onsite leadership created
field.
an environment that pushed the limits of teamwork to
BLEACHER FABRICATION
The structural design of Wrigley Field's bleachers
optimize methodology and minimize waste of materi-
maintains the historic nature of the ballpark and pre-
SALVAGE AND REUSE
als, time, and effort to generate maximum results.
sented some unique challenges for steel fabrication
Ultimately, there's nothing greener than to preserve
Through a collaborative and best-practice process, the
and erection. The design's connections, column sizes,
and restore an historic building, which is a better use
team transformed a 100-year-old iconic stadium into a
and thicknesses required a complex fabrication, weld-
of resources than a tear down to build a new LEED
ballpark that will provide first-class accommodations
ing, and installation plan, including a 3D model for
facility. Salvage and reuse were a big part of the res-
for generations of fans to enjoy. CA
the fabrication. The bleacher project alone took more
toration. Reuse means less new material was required
than 16,000 labor-hours to complete. It required three
than to build a new ballpark. Some examples include
Dwayne Lindsey is technical services manager with
different production facilities to supply the volume.
salvaging the stadium's existing steel and concrete
Pepper Construction, Chicago. Lindsey has worked in
After analyzing the 3D model, the team confirmed
structure and retaining the outfield brick wall. In ad-
the AEC industry for more than 17 years, specializing
that structural supports could be prefabricated offsite
dition, the ivy was kept covered and alive during con-
in virtual design and construction, and BIM. He may
and installed, essentially, like a large erector set.
struction to avoid being replanted, existing guardrails
be reached at 312-649-7628 or DLindsey@peppercon-
Planning and logistics were critical to keep neigh-
were reused in new assemblies, the exterior fascia was
struction.com. For more information, visit peppercon-
borhood traffic flowing. Each morning during the
reinstalled after the structure was completed, the icon-
struction.com or follow @pepperconstruct on Twitter.
bleacher project, Pepper received confirmation of what
steel members they would receive. Each trip was typically three or four hours so the riggers could plan their
afternoons around what would arrive within a few
hours, depending on the weather.
Sources listed below are linked at commercialarchitecturemagazine.com/1906pepper.
* Watch a time-lapse video of the entire construction process.
* Owners' representative: CAAICON, Denver, caaicon.com
they used as a staging area to store steel members not
* Watch a video about the micropile installation/technology.
yet ready for installation. During the off-season, the
* Architect: Stantec Architecture, Chicago, stantec.com
* Geotechnical Engineer: Hayward Baker, Hanover, MD,
haywardbaker.com
back half of Wrigley Field's Green Lot was also used as
* Architect: Populous, Kansas City, MO, populous.com
* Engineering firm: Thornton Tomasetti, New York City,
thorntontomasetti.com
a staging area for lay-down of arriving materials that
* Contractor: Pepper Const., Chicago, pepperconstruction.com
* Engineering firm: GEI Consultants, Chicago, geiconsultants.com
The steel contractor also had a yard in Chicago that
subcontractors still had to inspect or work on before
20
JUNE 2019
COMMERCI A L A RCHI T EC T UREM AG A ZINE.COM
http://www.pepperconstruction.com
http://www.pepperconstruction.com
http://www.commercialarchitecturemagazine.com/1906pepper
http://www.caaicon.com
http://www.haywardbaker.com
http://www.stantec.com
http://www.populous.com
http://www.thorntontomasetti.com
http://www.pepperconstruction.com
http://www.geiconsultants.com
Commercial Architecture June 2019
Table of Contents for the Digital Edition of Commercial Architecture June 2019
Commercial Architecture June 2019 - Cover1
Commercial Architecture June 2019 - Cover2
Commercial Architecture June 2019 - 1
Commercial Architecture June 2019 - 2
Commercial Architecture June 2019 - 3
Commercial Architecture June 2019 - 4
Commercial Architecture June 2019 - 5
Commercial Architecture June 2019 - 6
Commercial Architecture June 2019 - 7
Commercial Architecture June 2019 - 8
Commercial Architecture June 2019 - 9
Commercial Architecture June 2019 - 10
Commercial Architecture June 2019 - 11
Commercial Architecture June 2019 - 12
Commercial Architecture June 2019 - 13
Commercial Architecture June 2019 - 14
Commercial Architecture June 2019 - 15
Commercial Architecture June 2019 - 16
Commercial Architecture June 2019 - 17
Commercial Architecture June 2019 - 18
Commercial Architecture June 2019 - 19
Commercial Architecture June 2019 - 20
Commercial Architecture June 2019 - 21
Commercial Architecture June 2019 - 22
Commercial Architecture June 2019 - 23
Commercial Architecture June 2019 - 24
Commercial Architecture June 2019 - 25
Commercial Architecture June 2019 - 26
Commercial Architecture June 2019 - 27
Commercial Architecture June 2019 - 28
Commercial Architecture June 2019 - 29
Commercial Architecture June 2019 - 30
Commercial Architecture June 2019 - 31
Commercial Architecture June 2019 - 32
Commercial Architecture June 2019 - 35
Commercial Architecture June 2019 - 36
Commercial Architecture June 2019 - 37
Commercial Architecture June 2019 - 38
Commercial Architecture June 2019 - 39
Commercial Architecture June 2019 - 40
Commercial Architecture June 2019 - 41
Commercial Architecture June 2019 - 42
Commercial Architecture June 2019 - 43
Commercial Architecture June 2019 - 44
Commercial Architecture June 2019 - 45
Commercial Architecture June 2019 - 46
Commercial Architecture June 2019 - 47
Commercial Architecture June 2019 - 48
Commercial Architecture June 2019 - 49
Commercial Architecture June 2019 - 50
Commercial Architecture June 2019 - Cover3
Commercial Architecture June 2019 - Cover4
https://www.nxtbook.com/atp/cbp/201906
https://www.nxtbook.com/atp/cbp/201905
https://www.nxtbook.com/atp/cbp/201904
https://www.nxtbook.com/atp/cbp/201903
https://www.nxtbook.com/atp/cbp/201901
https://www.nxtbook.com/atp/cbp/201812
https://www.nxtbook.com/atp/cbp/201811
https://www.nxtbook.com/atp/cbp/201810
https://www.nxtbook.com/atp/cbp/201809
https://www.nxtbook.com/atp/cbp/201808
https://www.nxtbook.com/atp/cbp/201807
https://www.nxtbook.com/atp/cbp/201806
https://www.nxtbook.com/atp/cbp/201805
https://www.nxtbook.com/atp/cbp/201804
https://www.nxtbook.com/atp/cbp/201803
https://www.nxtbook.com/atp/cbp/201802
https://www.nxtbook.com/atp/cbp/201801
https://www.nxtbook.com/atp/cbp/201712
https://www.nxtbook.com/atp/cbp/201711
https://www.nxtbook.com/atp/cbp/201710
https://www.nxtbook.com/atp/cbp/201709
https://www.nxtbook.com/atp/cbp/201708
https://www.nxtbook.com/atp/cbp/201707
https://www.nxtbook.com/atp/cbp/201706
https://www.nxtbook.com/atp/cbp/201705
https://www.nxtbook.com/atp/cbp/201704
https://www.nxtbook.com/atp/cbp/201703
https://www.nxtbook.com/atp/cbp/201701
https://www.nxtbook.com/atp/cbp/201612
https://www.nxtbook.com/atp/cbp/201611
https://www.nxtbook.com/atp/cbp/201610
https://www.nxtbook.com/atp/cbp/201609
https://www.nxtbook.com/atp/cbp/201607
https://www.nxtbook.com/atp/cbp/201606
https://www.nxtbook.com/atp/cbp/201605
https://www.nxtbook.com/atp/cbp/201604
https://www.nxtbook.com/atp/cbp/201603
https://www.nxtbook.com/atp/cbp/201601
https://www.nxtbook.com/atp/cbp/201511
https://www.nxtbook.com/atp/cbp/201510
https://www.nxtbook.com/atp/cbp/201509
https://www.nxtbook.com/atp/cbp/201507
https://www.nxtbook.com/atp/cbp/201506
https://www.nxtbook.com/atp/cbp/201505
https://www.nxtbook.com/atp/cbp/201504
https://www.nxtbook.com/atp/cbp/201503
https://www.nxtbook.com/atp/cbp/20150102
https://www.nxtbook.com/atp/cbp/20141112
https://www.nxtbook.com/atp/cbp/201410
https://www.nxtbook.com/atp/cbp/201409
https://www.nxtbook.com/atp/cbp/20140708
https://www.nxtbook.com/atp/cbp/201406
https://www.nxtbook.com/atp/cbp/201405
https://www.nxtbook.com/atp/cbp/201404
https://www.nxtbook.com/atp/cbp/201403
https://www.nxtbook.com/atp/cbp/20140102
https://www.nxtbook.com/atp/cbp/201311
https://www.nxtbook.com/atp/cbp/201310
https://www.nxtbook.com/atp/cbp/201309
https://www.nxtbook.com/atp/cbp/201307
https://www.nxtbook.com/atp/cbp/201306
https://www.nxtbook.com/atp/cbp/201305
https://www.nxtbook.com/atp/cbp/201304
https://www.nxtbook.com/atp/cbp/201303
https://www.nxtbook.com/atp/cbp/20130102
https://www.nxtbook.com/atp/cbp/20121112
https://www.nxtbook.com/atp/cbp/201210
https://www.nxtbook.com/atp/cbp/201209
https://www.nxtbook.com/atp/cbp/20120708
https://www.nxtbook.com/atp/cbp/201206
https://www.nxtbook.com/atp/cbp/201205
https://www.nxtbook.com/atp/cbp/201204
https://www.nxtbook.com/atp/cbp/201203
https://www.nxtbook.com/atp/cbp/20120102
https://www.nxtbook.com/atp/cbp/20111112
https://www.nxtbook.com/atp/cbp/201110
https://www.nxtbook.com/atp/cbp/201109
https://www.nxtbook.com/atp/cbp/201107
https://www.nxtbook.com/atp/cbp/201106
https://www.nxtbook.com/atp/cbp/201105
https://www.nxtbook.com/atp/cbp/201104
https://www.nxtbook.com/atp/cbp/201103
https://www.nxtbook.com/atp/cbp/20110102
https://www.nxtbook.com/atp/cbp/20101112
https://www.nxtbook.com/atp/cbp/201010
https://www.nxtbookmedia.com