CIMA+ TECHNOLOGY SPOTLIGHT
TEMPUS - A PROVEN SOLUTION FOR
ONLINE CONTROL SYSTEM MIGRATIONS
UPGRADE
CONTROL SYSTEM
HARDWARE WITH
ZERO DOWNTIME,
AT THE PUSH OF
A BUTTON
 BY TIM RAUF
" What TEMPUS does is, it acts as a bridge
between the two systems, so that both
systems see the same information. You can
actually test and configure all of the new
logic with real field values, while the old
control system is still running the plant, "
says David Findlay, creator of the solution.
Images courtesy of CIMA+.
CONTROL SYSTEM MIGRATION is a process traditionally
done in one of two ways. One is to shut down the plant,
and perform the migration while the control system is offline.
From a capital cost perspective, this is the cheapest path, but
there's the matter of downtime costs that can add up quickly.
Another method is to do an online migration and move one
loop at a time, which allows systems to stay online, but has
limitations and can add a lot of complexity to the project.
TEMPUS, a new solution from CIMA+, takes the best from
both worlds, maintaining the simplicity and reliability of offline
migration, but with the benefits of retaining full control
for uninterrupted plant operation. Now being utilized across
Canada and the US, TEMPUS serves as a kind of handoff
point between a plant's old system and new.
Findlay came up with the idea for TEMPUS one day while
working on a traditional control system migration for a
customer of CIMA+ in Fort McMurray. As that process became
increasingly unwieldy and complicated, he reflected
on how better to conduct such an operation - one that was
cheaper, more reliable and less risky. Starting its life as a
napkin sketch, TEMPUS steadily evolved with new features
to check off these boxes. It premiered as a wholly unique
solution to a cumbersome problem.
The system itself works through a temporary hardware
installation, a small blue square module, that facilitates
online migrations. The modules are installed in parallel to
both the existing system and the new one. Modules are
installed just before system swingover, and removed immediately
after the new system's commissioning process
is complete. The solution works by using pierce probes, allowing
it to gain continuity with the existing system without
disrupting its signals.
22 | SUMMER 2022 | TECHNOLOGY ALBERTA

ASET Technology Alberta Summer 2022

Table of Contents for the Digital Edition of ASET Technology Alberta Summer 2022

Table of Contents
ASET Technology Alberta Summer 2022 - Cover1
ASET Technology Alberta Summer 2022 - Cover2
ASET Technology Alberta Summer 2022 - 3
ASET Technology Alberta Summer 2022 - Table of Contents
ASET Technology Alberta Summer 2022 - 5
ASET Technology Alberta Summer 2022 - 6
ASET Technology Alberta Summer 2022 - 7
ASET Technology Alberta Summer 2022 - 8
ASET Technology Alberta Summer 2022 - 9
ASET Technology Alberta Summer 2022 - 10
ASET Technology Alberta Summer 2022 - 11
ASET Technology Alberta Summer 2022 - 12
ASET Technology Alberta Summer 2022 - 13
ASET Technology Alberta Summer 2022 - 14
ASET Technology Alberta Summer 2022 - 15
ASET Technology Alberta Summer 2022 - 16
ASET Technology Alberta Summer 2022 - 17
ASET Technology Alberta Summer 2022 - 18
ASET Technology Alberta Summer 2022 - 19
ASET Technology Alberta Summer 2022 - 20
ASET Technology Alberta Summer 2022 - 21
ASET Technology Alberta Summer 2022 - 22
ASET Technology Alberta Summer 2022 - 23
ASET Technology Alberta Summer 2022 - 24
ASET Technology Alberta Summer 2022 - 25
ASET Technology Alberta Summer 2022 - 26
ASET Technology Alberta Summer 2022 - 27
ASET Technology Alberta Summer 2022 - 28
ASET Technology Alberta Summer 2022 - 29
ASET Technology Alberta Summer 2022 - 30
ASET Technology Alberta Summer 2022 - 31
ASET Technology Alberta Summer 2022 - 32
ASET Technology Alberta Summer 2022 - 33
ASET Technology Alberta Summer 2022 - 34
ASET Technology Alberta Summer 2022 - 35
ASET Technology Alberta Summer 2022 - 36
ASET Technology Alberta Summer 2022 - 37
ASET Technology Alberta Summer 2022 - 38
ASET Technology Alberta Summer 2022 - 39
ASET Technology Alberta Summer 2022 - 40
ASET Technology Alberta Summer 2022 - 41
ASET Technology Alberta Summer 2022 - 42
ASET Technology Alberta Summer 2022 - 43
ASET Technology Alberta Summer 2022 - B Cover
https://www.nxtbook.com/dawson/aset/ta_spring_2024
https://www.nxtbook.com/dawson/aset/ta_winter_2023
https://www.nxtbook.com/dawson/aset/ta_fall_2023
https://www.nxtbook.com/dawson/aset/ta_summer_2023
https://www.nxtbook.com/dawson/aset/ta_spring_2023
https://www.nxtbook.com/dawson/aset/ta_winter_2022
https://www.nxtbook.com/dawson/aset/ta_fall_2022
https://www.nxtbook.com/dawson/aset/ta_summer_2022
https://www.nxtbook.com/dawson/aset/ta_spring_2022
https://www.nxtbook.com/dawson/aset/ta_winter_2021
https://www.nxtbook.com/dawson/aset/ta_fall_2021
https://www.nxtbook.com/dawson/aset/ta_summer_2021
https://www.nxtbook.com/dawson/aset/ta_spring_2021
https://www.nxtbook.com/dawson/aset/ta_winter_2020
https://www.nxtbook.com/dawson/aset/ta_fall_2020
https://www.nxtbook.com/dawson/aset/ta_summer_2020
https://www.nxtbook.com/dawson/aset/ta_spring_2020
https://www.nxtbook.com/dawson/aset/ta_winter_2019
https://www.nxtbook.com/dawson/aset/ta_summer_2019
https://www.nxtbook.com/dawson/aset/ta_spring_2019
https://www.nxtbook.com/dawson/aset/ta_fall_dec2018
https://www.nxtbook.com/dawson/aset/aset55anniversary
https://www.nxtbook.com/dawson/aset/ta_spring_2018
https://www.nxtbook.com/dawson/aset/ta_winter_2018
https://www.nxtbook.com/dawson/aset/ta_fall_2017
https://www.nxtbook.com/dawson/aset/ta_spring_2017
https://www.nxtbook.com/dawson/aset/ta_winter_2017
https://www.nxtbook.com/dawson/aset/ta_fall_2016
https://www.nxtbook.com/dawson/aset/ta_summer_2016
https://www.nxtbook.com/dawson/aset/ta_spring_2016
https://www.nxtbook.com/dawson/aset/ta_winter_2016
https://www.nxtbook.com/dawson/aset/ta_fall_2015
https://www.nxtbook.com/dawson/aset/ta_summer_2015
https://www.nxtbook.com/dawson/aset/ta_spring_2015
https://www.nxtbookmedia.com