marchapril2021 - 21

BOARDING BRIDGES
Monaco said the team executed a
two to three week turn per gate, with
the start date at each gate offset by one
week. Once the project was underway,
they were taking a gate out of service
and putting a different gate back in
service each week.
" We had to phase the work. Multiple
activities and crews were closely
coordinated and worked together
including electricians, civil contractors,
ramp striping crews, cranes and of
course the bridge and equipment all
within one gate area. In this approach,
we were able to perform all the work at
the gate without impacting any adjacent
operations, which was much appreciated
by the airport and how we normally
perform our installations, " Pearson said.

Airport made this an all-inclusive
turn-key project that, in addition to
the PBB equipment itself, included all
the necessary foundations, electrical
upgrades, low voltage improvements,
plumbing work, access control, fire
alarm connections, ramp striping and
exterior building improvements to
complete the entire scope of a gate
replacement, " said Pearson. " This
streamlined the entire process for the

airport, resulting in a well-coordinated
project completed ahead of schedule and
within budget.
" Getting through that turn-key
delivery decision process, making sure
the design is correct, and then issuing a
single package was a great decision by
ORF and one we would suggest for any
airport considering a passenger boarding
bridge replacement program. " 

The Benefits of Holism
With only some finalizing left to be done
for the iOPS system, ORF is reaping
the rewards of their holistic approach to
the project. Bass said it's been a major
benefit from a maintenance perspective.
" Because I can purchase spare parts,
and they work on every single one of
the bridges, I don't have to keep as many
spare parts because I don't have a variety.
And it really reduces on my overall costs
for keeping stock, " he said.
" And my maintenance costs, because
they're not unique, each one is a repeat
of each other, I only have to train my
staff on one particular type of passenger
loading bridge, and then they can
basically work on any of them, " Bass
continued. " And so, now I'm able to
take over a lot of maintenance items
that usually you had to have a significant
amount of knowledge since each
manufacturer is a little bit different in
how they construct and how they wire
up their particular passenger loading
bridges. This is not the case for us
now. So, when they're trained, they
can basically work on majority of our
passenger loading bridges, which has
been a big cost savings to the airport. "
Aside from ORF saving time and
saving money, which allowed them to
add another bridge to the project, the
holistic approach also proved beneficial
on the construction side.
" They didn't procure just boarding
bridges and issue separate contracts for
other scopes of this project. Norfolk

Read,
Learn,
Grow
Never miss an issue.
Renew your AB
subscription/
Update your
contact information
Type in your
account number (see your mailing
label) and last name to access your
information.

Get an AB
subscription
Borrowing from a
colleague? Sign up
today for your own
FREE subscription!

www.aviationpros.com/subscribe
Don't like updating online?
Contact customer service at 847-559-7598.

MARCH/APRIL 2021 \ AVIATIONPROS.COM / 21


http://www.aviationpros.com/subscribe http://www.AVIATIONPROS.COM

marchapril2021

Table of Contents for the Digital Edition of marchapril2021

The $7 Million Man
Industry Update
A New Normal in Airport Parking and Transportation
The Rise of Robots
Boarding Bridges the Holistic Way
A Brave New World
The Trouble with Tribal Knowledge
Doing it Right: Public Sector FBOs
Reconstructing One of New England's Longest Commericial Service Runways
Designing a Modern Lighthouse
Sensor Technology's One-Two Punch: Improving Winter Maintenance Operations and Meeting ICAO GRF Regulations
Caution: Closure Ahead
marchapril2021 - 1
marchapril2021 - 2
marchapril2021 - 3
marchapril2021 - 4
marchapril2021 - The $7 Million Man
marchapril2021 - Industry Update
marchapril2021 - 7
marchapril2021 - 8
marchapril2021 - 9
marchapril2021 - 10
marchapril2021 - 11
marchapril2021 - A New Normal in Airport Parking and Transportation
marchapril2021 - 13
marchapril2021 - The Rise of Robots
marchapril2021 - 15
marchapril2021 - 16
marchapril2021 - 17
marchapril2021 - Boarding Bridges the Holistic Way
marchapril2021 - 19
marchapril2021 - 20
marchapril2021 - 21
marchapril2021 - A Brave New World
marchapril2021 - 23
marchapril2021 - 24
marchapril2021 - 25
marchapril2021 - The Trouble with Tribal Knowledge
marchapril2021 - 27
marchapril2021 - 28
marchapril2021 - Doing it Right: Public Sector FBOs
marchapril2021 - 30
marchapril2021 - 31
marchapril2021 - Reconstructing One of New England's Longest Commericial Service Runways
marchapril2021 - 33
marchapril2021 - 34
marchapril2021 - 35
marchapril2021 - Designing a Modern Lighthouse
marchapril2021 - 37
marchapril2021 - Sensor Technology's One-Two Punch: Improving Winter Maintenance Operations and Meeting ICAO GRF Regulations
marchapril2021 - 39
marchapril2021 - Caution: Closure Ahead
marchapril2021 - 41
marchapril2021 - 42
marchapril2021 - 43
marchapril2021 - 44
https://www.nxtbook.com/endeavor/airportbusiness/march-april-2024
https://www.nxtbook.com/endeavor/airportbusiness/january-february-2024
https://www.nxtbook.com/endeavor/airportbusiness/november-december-2023
https://www.nxtbook.com/endeavor/airportbusiness/september-october-2023
https://www.nxtbook.com/endeavor/airportbusiness/july-august
https://www.nxtbook.com/endeavor/airportbusiness/may-june-2023
https://www.nxtbook.com/endeavor/airportbusiness/march-april-2023
https://www.nxtbook.com/endeavor/airportbusiness/january-february-2023
https://www.nxtbook.com/endeavor/airportbusiness/november-december-2022
https://www.nxtbook.com/endeavor/airportbusiness/september-october-2022
https://www.nxtbook.com/endeavor/airportbusiness/july-august-2022
https://www.nxtbook.com/endeavor/airportbusiness/may-june-2022
https://www.nxtbook.com/endeavor/airportbusiness/march-april_2022
https://www.nxtbook.com/endeavor/airportbusiness/january-february-2022
https://www.nxtbook.com/endeavor/airportbusiness/november-december-2021
https://www.nxtbook.com/endeavor/airportbusiness/september-october_2021
https://www.nxtbook.com/endeavor/airportbusiness/july-august_2021
https://www.nxtbook.com/endeavor/airportbusiness/airport-business_may-june_2021
https://www.nxtbook.com/endeavor/airportbusiness/marchapril2021
https://www.nxtbook.com/endeavor/airportbusiness/januaryfebruary2021
https://www.nxtbook.com/endeavor/airportbusiness/december2020
https://www.nxtbook.com/endeavor/airportbusiness/Airport_Business_November_2020
https://www.nxtbook.com/endeavor/airportbusiness/october2020
https://www.nxtbook.com/endeavor/airportbusiness/augustseptember2020
https://www.nxtbook.com/endeavor/airportbusiness/Airport_Business_June-July_2020
https://www.nxtbook.com/endeavor/airportbusiness/may2020
https://www.nxtbook.com/endeavor/airportbusiness/april2020
https://www.nxtbook.com/endeavor/airportbusiness/Airport_Business_February-March_2020
https://www.nxtbook.com/endeavor/airportbusiness/Airport_Business_December2019-January2020
https://www.nxtbook.com/endeavor/airportbusiness/november2019
https://www.nxtbook.com/endeavor/airportbusiness/october2019
https://www.nxtbook.com/endeavor/airportbusiness/augustseptember2019
https://www.nxtbook.com/endeavor/airportbusiness/Airport_Business_June-July_2019
https://www.nxtbook.com/endeavor/airportbusiness/may2019
https://www.nxtbook.com/endeavor/airportbusiness/april2019
https://www.nxtbook.com/endeavor/airportbusiness/februarymarch2019
https://www.nxtbookmedia.com