Underground Construction - December 2020 - 23

Directional Drilling

Intersect HDD Gets Better with Experience
Jeff Griffin | Senior Editor

An " intersect " project may be the most complex application in
horizontal directional drilling (HDD).
Two pilot holes - one at each end of the projected bore path
- meet somewhere in between to make a single pilot hole for
pulling in the product. Each segment usually is long, and the
diameter of the pipe being installed is larger. The intersects'
point of connection may be under a river or larger body of water.
For the two bore paths to intersect takes meticulous planning
and precise execution. While, today, an intersect project is not
uncommon, few contractors have the equipment and capabilities
to undertake an intersect project and the challenges it presents.

Early days
The first successful intersect was completed in 2003 by Michels
Directional Crossings for a segment of Maritimes and Northeast
Duke Energy Hub-Line Project in Boston. The Georges Island
HDD crossing a was 5,174-foot-long, hard-rock, water-to-water
crossing to install 30-inch diameter pipe.
Lengths of intersects and diameters of product installed have
steadily increased in the years since the first intersect installation.
Underground Construction queried representatives from
three veteran HDD contractors with several successful intersect
projects on their resumes about this challenging method of
underground construction.
Michels Directional Crossings,
Jeffrey S. Mueller, senior vice president
Intersects have become common in the HDD industry and are used
for a variety of reasons to minimize risk and increase productivity.
Various circumstances lead us to consider pilot hole intersects
instead of single bore. The most obvious one is length. Depending
on diameter of the pipe and the geological conditions, at a certain
point even the most powerful rig would not have the horsepower
needed to provide the thrust and rotary torque required to cross
the entire span.
Other factors are the anticipated annular pressure of
drilling fluid required to remove the cuttings, right-of-way
considerations and time frames. If timing is tight, it theoretically
takes less time for two rigs to drill from opposite sides of a
project and meet in the middle than it would for one rig to
complete the entire drill. Right-of-way restrictions determine
where the product pipe is staged and assembled for pullback.
As with all HDD projects, accuracy and attention to details
are critical to pilot-hole intersect projects. With two rigs
drilling from opposite sides, tracking tools are important to
ensure each rig stays on the predetermined alignment. Severe
pilot-hole misalignment can cause tool failure, or the product
pipe to become lodged due to inappropriate radii through the
intersect transition.

Typically, a tangent section of the bore, rather than a midpoint, is selected as the location of an intersection. As technology
has advanced in this industry over the past two decades, the point
of intersect is not as critical or difficult a decision as it had been
in the method's infancy. The sophistication and skill of those
involved in this industry have grown exponentially.
We use a variety of equipment, including surface guidance,
magnetic survey instruments and gyroscopic tooling. For most
drills, primary and secondary tracking systems are important.
Many factors affect our decisions on the best methods and
equipment for picking up signals, for and determining the precise
position of the drill heads.
Downhole guidance sensors are utilized to align the drill paths,
resulting in a successful intersect. Many intersects are completed
underwater because HDD is typically done in conditions where
traditional or open-cut installations would not be possible - and
that is often under water or in other environmentally sensitive
areas. The execution of the intersect does not vary based on what
is above the location.
UCONonline.com | DECEMBER 2020

23


http://www.UCONonline.com

Underground Construction - December 2020

Table of Contents for the Digital Edition of Underground Construction - December 2020

Contents
Underground Construction - December 2020 - Cover1
Underground Construction - December 2020 - Cover2
Underground Construction - December 2020 - Contents
Underground Construction - December 2020 - 4
Underground Construction - December 2020 - 5
Underground Construction - December 2020 - 6
Underground Construction - December 2020 - 7
Underground Construction - December 2020 - 8
Underground Construction - December 2020 - 9
Underground Construction - December 2020 - 10
Underground Construction - December 2020 - 11
Underground Construction - December 2020 - 12
Underground Construction - December 2020 - 13
Underground Construction - December 2020 - 14
Underground Construction - December 2020 - 15
Underground Construction - December 2020 - 16
Underground Construction - December 2020 - 17
Underground Construction - December 2020 - 18
Underground Construction - December 2020 - 19
Underground Construction - December 2020 - 20
Underground Construction - December 2020 - 21
Underground Construction - December 2020 - 22
Underground Construction - December 2020 - 23
Underground Construction - December 2020 - 24
Underground Construction - December 2020 - 25
Underground Construction - December 2020 - 26
Underground Construction - December 2020 - 27
Underground Construction - December 2020 - 28
Underground Construction - December 2020 - 29
Underground Construction - December 2020 - 30
Underground Construction - December 2020 - 31
Underground Construction - December 2020 - 32
Underground Construction - December 2020 - 33
Underground Construction - December 2020 - 34
Underground Construction - December 2020 - 35
Underground Construction - December 2020 - 36
Underground Construction - December 2020 - 37
Underground Construction - December 2020 - 38
Underground Construction - December 2020 - 39
Underground Construction - December 2020 - 40
Underground Construction - December 2020 - 41
Underground Construction - December 2020 - 42
Underground Construction - December 2020 - 43
Underground Construction - December 2020 - 44
Underground Construction - December 2020 - 45
Underground Construction - December 2020 - 46
Underground Construction - December 2020 - 47
Underground Construction - December 2020 - 48
Underground Construction - December 2020 - 49
Underground Construction - December 2020 - 50
Underground Construction - December 2020 - Cover3
Underground Construction - December 2020 - Cover4
https://www.nxtbook.com/gulfenergyinfo/gulfpub/underground-construction-december-2022
https://www.nxtbook.com/gulfenergyinfo/gulfpub/uc_202211
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202210
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202209
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202208
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202207
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202206
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202205
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202204
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202203
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202202
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202201
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202112
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202111
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202110
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202109
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202108
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202107
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202106
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202105
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202104
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202103
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202102
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202101
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202012
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202011
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202010
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202009
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202008
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202007
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202006
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202005
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202004
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202003
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202002
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202001
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201912
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201911
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201910
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201909
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201908
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201907
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201906
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_summer2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201905
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201904
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201903
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_winter2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201902
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201901
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201812
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201811
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201810
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201809
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201808
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201807
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201806
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201805
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201804
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201803
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201802
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201801
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201712
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201711
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201710
https://www.nxtbook.com/nxtbooks/gulfpub/uc_ditchwitch
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201709
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201708
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201707
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201706
https://www.nxtbookmedia.com